716-718 1/2 E 107TH ST 90002
Certificate Information: 716-718 1/2 E 107TH ST 90002
- Application / Permit
- 21016-20000-19284
- Plan Check / Job No.
- B21VN09741
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) 17'-5" X 22' ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER PER GCS 65852.2(e)(1)(D). ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- CofO Issued on 2/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/1/2021 | RAPHAEL ROSAS |
| Issued | 9/10/2021 | APPLICANT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| CofO in Progress | 2/8/2022 | JOSEPH MCGARRY |
| Permit Finaled | 2/10/2022 | DEROLD HAUFF |
| CofO Issued | 2/10/2022 | DEROLD HAUFF |
| Permit Finaled | 2/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 8/17/2021 | MICHAEL SOTO |
| Sewer availability | Cleared | 8/20/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | California Green Home Solutions; Lic. No.: 1043877-B | 7020 HAYVENHURST AVE STE B VAN NUYS, CA 91406 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/24/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/24/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/24/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/7/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/7/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 10/7/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/7/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Approved | EUGENE CASSIDY |
| Insulation | 10/12/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/19/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/19/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/29/2021 | Approved | EUGENE CASSIDY |
| Shower Pan | 10/29/2021 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 11/1/2021 | Approved | EUGENE CASSIDY |
| Sewer | 12/22/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 12/30/2021 | Approved | EUGENE CASSIDY |
| Sewer | 12/30/2021 | Partial Approval | EUGENE CASSIDY |
| Final | 1/20/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 1/20/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/20/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/7/2022 | Approved | JOSEPH MCGARRY |
| Final | 2/7/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 2/7/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 2/7/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/7/2022 | Approved | JOSEPH MCGARRY |