7228 N AMIGO AVE 1/2 91335

Certificate Information: 7228 N AMIGO AVE 1/2 91335

Application / Permit
21016-20000-19219
Plan Check / Job No.
B21VN09726
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
*ePLAN CHECK* CONVERSION OF REC ROOM (430 SQ FT) IN 22 UNIT (E) APARTMENT BUILDING TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 12/21/2021
Issuing Office
Current Status
CofO Issued on 2/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 LAMAR DAVIS
Corrections Issued 8/31/2021 LAMAR DAVIS
Quality Review Completed 9/9/2021 WING SUEN
Applicant returned to address corrections 9/20/2021 LAMAR DAVIS
Applicant returned to address corrections 10/6/2021 LAMAR DAVIS
Applicant returned to address corrections 10/27/2021 LAMAR DAVIS
Plan Check Approved 11/30/2021 LAMAR DAVIS
Issued 12/21/2021 APPLICANT
CofO in Progress 6/14/2022 CAMERON CHABAN
Permit Finaled 2/27/2023 JEFFREY DURAN
CofO Issued 2/27/2023 JEFFREY DURAN
Permit Finaled 2/27/2023 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 9/14/2021 GABRIEL ROBLES
Sewer availability Cleared 9/14/2021 GABRIEL ROBLES
"D" conditions Cleared 9/15/2021 DANG NGUYEN
"T" removal Cleared 9/15/2021 DANG NGUYEN
CPC Cleared 9/15/2021 DANG NGUYEN
Miscellaneous Cleared 9/15/2021 DANG NGUYEN
Miscellaneous Cleared 9/15/2021 DANG NGUYEN
ZA Case Cleared 9/15/2021 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 10/7/2021 GABRIEL ROBLES
"Q" conditions Cleared 10/10/2021 LAURA FRAZIN-STEELE
Supp. Use District POD/CDO/TDO Cleared 10/10/2021 LAURA FRAZIN-STEELE
DAS Clearance Cleared 10/18/2021 SHINE LIN
Fire Marshal Fire Life Safety Cleared 10/20/2021 VIDAL GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/9/2022 Conditional Approval CAMERON CHABAN
Final 3/16/2022 Partial Inspection CAMERON CHABAN
Smoke Detectors 3/16/2022 Approved CAMERON CHABAN
Wood Frame 3/16/2022 Approved CAMERON CHABAN
Final 6/7/2022 Partial Inspection CAMERON CHABAN
Final 6/14/2022 OK to Issue CofO CAMERON CHABAN