7704-7706 N PASO ROBLES AVE 91406
Certificate Information: 7704-7706 N PASO ROBLES AVE 91406
- Application / Permit
- 21016-20000-19217
- Plan Check / Job No.
- B21VN09723
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT MASTER BEDROOM TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code65852.2(e)(1)(A) and65852.2 IN (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/23/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | SERGIO MUNIZ |
| Corrections Issued | 8/2/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/9/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/26/2021 | SERGIO MUNIZ |
| Plan Check Approved | 12/15/2021 | SERGIO MUNIZ |
| Issued | 12/23/2021 | APPLICANT |
| Building Plans Picked Up | 7/7/2022 | APPLICANT |
| CofO in Progress | 9/30/2022 | RAUL OLAGI |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/15/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 5/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| Pre-Inspection | 5/9/2022 | Approved | RAUL OLAGI |
| Smoke Detectors | 5/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 5/31/2022 | Approved | RAUL OLAGI |
| Gas Test | 5/31/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 5/31/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/31/2022 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 5/31/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/8/2022 | Approved | ALAN MORELOS |
| Gas Test | 6/8/2022 | Partial Approval | ALAN MORELOS |
| HVAC-Rough | 6/8/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 6/8/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 6/14/2022 | Approved | DEANDRE HOFFMAN |
| Gas Test | 6/14/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 6/28/2022 | No Access for Inspection | ALAN MORELOS |
| Final | 6/28/2022 | No Access for Inspection | ALAN MORELOS |
| Gas Test | 6/28/2022 | No Access for Inspection | ALAN MORELOS |
| Smoke Detectors | 6/28/2022 | No Access for Inspection | ALAN MORELOS |
| ELECTRICAL-Final | 7/1/2022 | Approved | ALAN MORELOS |
| Final | 7/1/2022 | Corrections Issued | ALAN MORELOS |
| HVAC-Final | 7/1/2022 | Approved | ALAN MORELOS |
| PLUMBING-Final | 7/1/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/7/2022 | No Access for Inspection | DEANDRE HOFFMAN |
| Final | 7/7/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Smoke Detectors | 7/7/2022 | No Access for Inspection | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 9/30/2022 | Approved | RAUL OLAGI |
| Final | 9/30/2022 | OK to Issue CofO | RAUL OLAGI |
| Smoke Detectors | 9/30/2022 | Approved | RAUL OLAGI |