14002 W ADDISON ST 91423

Certificate Information: 14002 W ADDISON ST 91423

Application / Permit
21016-20000-19028
Plan Check / Job No.
B21VN09598
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-4" X 28'-4" DETACHED GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 7/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2021 APPLICANT
Assigned to Plan Check Engineer 7/30/2021 RAPHAEL ROSAS
Corrections Issued 8/1/2021 RAPHAEL ROSAS
Applicant returned to address corrections 10/26/2021 RAPHAEL ROSAS
Plan Check Approved 12/12/2021 RAPHAEL ROSAS
Building Plans Picked Up 12/20/2021 APPLICANT
Issued 12/22/2021 APPLICANT
CofO in Progress 6/30/2023 JOHN COLEMAN
CofO Issued 7/13/2023 DANIEL ORRANTE
Permit Finaled 7/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/11/2021 CARLOS AGUILERA
Sewer availability Cleared 8/11/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/18/2021 CARLOS AGUILERA
ZI Cleared 9/10/2021 LAUREN PADICK
Construction near power lines Cleared 10/13/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Vahabzadeh,, Reza; Lic. No.: S6538 13961 MOORPARK ST APT 207      SHERMAN OAKS, CA 91423

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/25/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/9/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/11/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/9/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 6/9/2022 Corrections Issued MISAEL ESPARZA
Green Building Rough 6/9/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 6/9/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/9/2022 Approved MISAEL ESPARZA
Underground Mechanical 7/21/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/11/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 8/11/2022 Approved MISAEL ESPARZA
Green Building Rough 8/11/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/11/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 8/11/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/1/2022 Approved MISAEL ESPARZA
Insulation 9/13/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/13/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Corrections Issued MISAEL ESPARZA
Drywall Nailing 9/22/2022 Partial Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Not Ready for Inspection DEANDRE HOFFMAN
Drywall Nailing 9/27/2022 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved MISAEL ESPARZA
Drywall Nailing 10/4/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/13/2023 Approved MISAEL ESPARZA
Final 3/13/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 3/13/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/13/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 3/13/2023 Corrections Issued MISAEL ESPARZA
Final 4/24/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 4/24/2023 Approved MISAEL ESPARZA
Smoke Detectors 4/24/2023 Approved MISAEL ESPARZA
Final 6/16/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Final 6/30/2023 Approved JOHN COLEMAN
Final 6/30/2023 OK to Issue CofO JOHN COLEMAN
HVAC-Final 6/30/2023 Approved JOHN COLEMAN
PLUMBING-Final 6/30/2023 Approved JOHN COLEMAN
Service/Power Release 6/30/2023 Approved JOHN COLEMAN