2465 S PENMAR AVE 90291

Certificate Information: 2465 S PENMAR AVE 90291

Application / Permit
21016-20000-18945
Plan Check / Job No.
B21VN09562
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT IN (E) SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c)and (e). ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
Permit Issued
Issued on 10/22/2021
Issuing Office
Current Status
CofO Issued on 6/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/30/2021 SERGIO MUNIZ
Corrections Issued 8/2/2021 SERGIO MUNIZ
Plan Check Approved 9/28/2021 SERGIO MUNIZ
Building Plans Picked Up 10/14/2021 APPLICANT
Issued 10/22/2021 APPLICANT
CofO in Progress 6/7/2022 PATRICK QUALEY
Permit Finaled 6/9/2022 DANIEL ORRANTE
CofO Issued 6/9/2022 DANIEL ORRANTE
Permit Finaled 6/9/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/12/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/19/2021 DINAH GARIN
Sewer availability Cleared 8/19/2021 DINAH GARIN
Specific Plan Cleared 9/13/2021 ROBERT SANCHEZ

Contact Information

Contractor Ahn'S Construction; Lic. No.: 1022756-B 13330 BLOOMFIELD AVENUE   SUITE 220    NORWALK, CA 90650

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2021 Corrections Issued ENRIQUE MIRELES
Deputy Drilled-In Anchors 11/30/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 12/2/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 12/9/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/10/2022 Approved ENRIQUE MIRELES
Green Building Rough 1/10/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/10/2022 Approved ENRIQUE MIRELES
Insulation 1/19/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/14/2022 Approved STEPHANIE SWANSON
Drywall Nailing 2/14/2022 Approved STEPHANIE SWANSON
HVAC-Rough 2/14/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 2/14/2022 Approved STEPHANIE SWANSON
Final 4/18/2022 Corrections Issued PATRICK QUALEY
Green Building Final 4/18/2022 Approved PATRICK QUALEY
HVAC-Final 4/18/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/18/2022 SGSOV Approved PATRICK QUALEY
Smoke Detectors 4/18/2022 Approved PATRICK QUALEY
Final 5/31/2022 Conditional Approval PATRICK QUALEY
ELECTRICAL-Final 6/3/2022 Approved PATRICK QUALEY
Final 6/3/2022 OK to Issue CofO PATRICK QUALEY
HVAC-Final 6/3/2022 Approved PATRICK QUALEY
PLUMBING-Final 6/3/2022 Approved PATRICK QUALEY