12745 W HANOVER ST 90049
Certificate Information: 12745 W HANOVER ST 90049
- Application / Permit
- 21016-20000-18883
- Plan Check / Job No.
- B21VN09515
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- REMODEL (E) RECROOM AND TURN (E) ALQ INTO THEATRE ROOM WITH NEW 13'9" X 22'-0" GYM. AND 10'x22' PATIO COVER
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Current Status
- Issued on 8/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | JESSE ARELLANO |
| Corrections Issued | 8/6/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/2/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/3/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/16/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/26/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/19/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/14/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/28/2022 | JESSE ARELLANO |
| Plan Check Approved | 7/1/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Issued | 8/1/2022 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/17/2021 | PABLO ESTRADA |
| Grading Pre-Inspection | Cleared | 9/9/2021 | TIMOTHY POWELL |
| Hydrant and Access approval | Cleared | 10/9/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 11/17/2021 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | TRACY TATE |
| Green Code | Cleared | 5/19/2022 | JESSE ARELLANO |
Contact Information
| Architect | Yotnegparian,, Alain Levon; Lic. No.: C26374 | 11541 DONA PEPITA PLACE STUDIO CITY, CA 91604 |
| Contractor | Rattigan Construction; Lic. No.: 760004-B | 11549 DILLING ST STUDIO CITY, CA 91604 |
| Engineer | Koh,, William Kim; Lic. No.: S3473 | 5695 STARWOOD CT WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2022 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 8/15/2022 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 10/3/2022 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 10/4/2022 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/27/2022 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/17/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/17/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/14/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/14/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/14/2022 | Partial Approval | KEVIN SARGSYAN |
| Structural Steel Frame | 12/19/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 1/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 1/27/2023 | Conditional Approval | MICHAEL PELHAM |
| Structural Steel Frame | 2/24/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Structural Steel Frame | 2/28/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/16/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 11/2/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 11/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 3/13/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/13/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/18/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/26/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/28/2024 | Partial Approval | MICHAEL PELHAM |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | MICHAEL PELHAM |
| Insulation | 6/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 6/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Insulation | 6/6/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 6/6/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 6/11/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/24/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/8/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/7/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/7/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 1/7/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 5/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 5/23/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 7/25/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 7/31/2025 | Approved | HERBERT GIRON |
| PLUMBING-Final | 8/13/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 8/25/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/25/2025 | Approved | HERBERT GIRON |
| Special/Order Compliance | 8/25/2025 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 8/28/2025 | Approved | HERBERT GIRON |
| Final | 9/2/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 9/2/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Approved | MICHAEL ALLEN |
| Final | 9/9/2025 | Not Ready for Inspection | HERBERT GIRON |