7753-7755 N DUCOR AVE 91304

Certificate Information: 7753-7755 N DUCOR AVE 91304

Application / Permit
21016-20000-18882
Plan Check / Job No.
B21VN09512
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18' X 24' ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Issued on 5/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2021 APPLICANT
Assigned to Plan Check Engineer 7/28/2021 RAPHAEL ROSAS
Corrections Issued 7/29/2021 RAPHAEL ROSAS
Applicant returned to address corrections 6/6/2022 RAPHAEL ROSAS
Plan Check Approved 7/18/2022 RAPHAEL ROSAS
Building Plans Picked Up 7/18/2022 APPLICANT
Issued 7/21/2022 APPLICANT
CofO in Progress 5/26/2023 CHRIS CHRISTENSEN
CofO Issued 5/31/2023 JOHN JANSON
Permit Finaled 5/31/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/24/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/24/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/24/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Agoura Construction And Inspection Services; Lic. No.: 840985-B P O BOX 276      MOORPARK, CA 93020
Engineer Salehi,, Mohammad Reza Tom; Lic. No.: C50447 P O BOX 17881      ENCINO, CA 91416

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/1/2022 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 8/1/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/16/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/16/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/16/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 8/16/2022 Approved CHRIS CHRISTENSEN
Sewer 8/16/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/29/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 8/29/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/29/2022 Approved CHRIS CHRISTENSEN
Shower Pan 8/29/2022 Approved CHRIS CHRISTENSEN
Wood Frame 8/29/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/6/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 9/6/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 9/19/2022 Approved JUSTIN HAWLEY
Green Building Rough 9/19/2022 Not Ready for Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 9/27/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 9/27/2022 Approved CHRIS CHRISTENSEN
Insulation 9/27/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/27/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 9/28/2022 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 10/13/2022 Approved JUSTIN HAWLEY
Insulation 10/13/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/13/2022 Approved JUSTIN HAWLEY
Final 2/24/2023 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 2/24/2023 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready KRISTEN CAUSEY
Smoke Detectors 2/24/2023 Not Ready for Inspection KRISTEN CAUSEY
Final 3/29/2023 Not Ready for Inspection SEAN WIRCH
Green Building Final 3/29/2023 Not Ready for Inspection SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Not Ready SEAN WIRCH
Smoke Detectors 3/29/2023 Corrections Issued SEAN WIRCH
Final 4/27/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 4/27/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/27/2023 Approved CHRIS CHRISTENSEN