21314 W LASSEN ST 91311
Certificate Information: 21314 W LASSEN ST 91311
- Application / Permit
- 21016-20000-18880
- Plan Check / Job No.
- B21VN09508
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- SUPPLEMENTAL PERMIT TO 17016-20000-10189 TO REVISE SCOPE OF WORK TO - REMOVE 7837 SQ FT MEZZANINE AREA AND 4130 SQ FT OFFICE PORTION OF SECOND FLOOR. VOLUNTARY SEISMIC UPGRADE AND ROOF BEAM STRENGTHENING PER ENGINEER.
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 8/31/2021 | JEROME MAGAT PALMA |
| Quality Review Completed | 9/13/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/19/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 11/23/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/14/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/21/2021 | APPLICANT |
| Issued | 12/29/2021 | APPLICANT |
| CofO in Progress | 6/15/2022 | JEFFREY FULTON |
| CofO Issued | 8/19/2022 | JEFFREY DURAN |
| Permit Finaled | 8/19/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 10/26/2021 | OLLIE CARTER |
| Fire Marshal Fire Life Safety | Cleared | 12/14/2021 | WILLIAM JOHNS |
Contact Information
| Architect | Pedroso,, Gonzalo J; Lic. No.: C26455 | 13612 DEERING LANE MOORPARK, CA 93021 |
| Contractor | Dgr Construction Company Inc; Lic. No.: 1010921-B | 12401 SLAUSON AVE UNIT A WHITTIER, CA 90606 |
| Engineer | Hanna,, Emil R; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/5/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Pre-Inspection | 1/5/2022 | Corrections Issued | JEFFREY FULTON |
| Reinforced Masonry Frame | 1/5/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 1/5/2022 | Approved | JEFFREY FULTON |
| Wood Frame | 2/7/2022 | Approved | JEFFREY FULTON |
| Final | 4/4/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 4/4/2022 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | JEFFREY FULTON |
| Final | 4/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 5/9/2022 | OK to Issue CofO | JEFFREY FULTON |