811 S APPELBY ST 90291
Certificate Information: 811 S APPELBY ST 90291
- Application / Permit
- 21016-20000-18771
- Plan Check / Job No.
- B21VN09451
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD FOR (N) BATHROOMS, KITCHEN, CLOSET AND DINING ROOM. VAULT CEILING AT LIVING ROOM AREA. NEW WINDOWS AND INFILL WINDOWS THROUHGOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- Issued on 9/8/2021
Permit Application Status History
| Submitted | 7/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/29/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 8/16/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| Issued | 9/8/2021 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Rosegold Builders Inc; Lic. No.: 1041947-B | 12200 RIVERSIDE DRIVE UNIT 4 VALLEY VILLAGE, CA 91607 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 9/29/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/18/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 10/18/2021 | Partial Inspection | DAVID FEILER |
| HVAC-Rough | 10/18/2021 | Partial Inspection | DAVID FEILER |
| PLUMBING-Rough | 10/18/2021 | Partial Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 11/3/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| ELECTRICAL-Rough | 11/3/2021 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 11/3/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Wood Frame | 11/3/2021 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 11/17/2021 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 11/17/2021 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 11/17/2021 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 11/17/2021 | Approved | RICHARD STEINBACH |
| Wood Frame | 11/17/2021 | Approved | RICHARD STEINBACH |
| Insulation | 12/1/2021 | Approved | BOBBY KEY |
| Drywall Nailing | 12/14/2021 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Approved | BOBBY KEY |
| Shower Pan | 12/14/2021 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/30/2021 | Partial Approval | JOHNNY MIRANDA |
| Final | 5/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 5/23/2022 | Approved | JESUS RODRIGUEZ |