450 N HARPER AVE 90048
Certificate Information: 450 N HARPER AVE 90048
- Application / Permit
- 21016-20000-18717
- Plan Check / Job No.
- B21VN09418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGAE TO ADU (18'-6"x19'-0"), 318 SQFT PER GCS 65852.2(e)(1)(A
- Permit Issued
- Issued on 9/13/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/13/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | PETER MOSESIAN |
| Corrections Issued | 8/22/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| Plan Check Approved | 11/9/2021 | PETER MOSESIAN |
| Issued | 9/13/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2021 | CELINA MORENO |
| Sewer availability | Cleared | 9/14/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 10/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/5/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 3/27/2025 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Partial Approval | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Partial Approval | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/25/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/15/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 5/15/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 5/15/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 6/5/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 6/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 6/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 6/5/2025 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 6/5/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 6/18/2025 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 6/18/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 6/30/2025 | Corrections Issued | JOSE MACIAS |
| METHANE-Rough | 6/30/2025 | Not Ready for Inspection | JOSE MACIAS |
| Insulation | 8/18/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 8/29/2025 | Not Ready for Inspection | JOSE MACIAS |
| Drywall Nailing | 8/29/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 8/29/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/29/2025 | Not Ready for Inspection | JOSE MACIAS |
| Shower Pan | 9/18/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 9/22/2025 | Approved | RONNIE MINDANAO |