661 N LACHMAN LANE 90272
Certificate Information: 661 N LACHMAN LANE 90272
- Application / Permit
- 21016-20000-18635
- Plan Check / Job No.
- X21VN04663
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Window (25) and door (7) change-out (same size & type) for residential buildings. Re-stucco for residential buildings. Replacement of damaged framing members (less than 10% of replacement cost of building) for houses and duplexes (not including decks). Re-roof with Class A or B roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing (28) Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b)2B.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/12/2022
Permit Application Status History
| No Progress | 7/19/2021 | BLANCA MORALES |
| Issued | 7/20/2021 | APPLICANT |
| Permit Finaled | 4/12/2022 | ANDREW NAVE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 7/20/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/28/2021 | Partial Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 10/28/2021 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 11/4/2021 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 11/4/2021 | Not Ready for Inspection | ANDREW NAVE |
| Insulation | 11/8/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/8/2021 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 11/10/2021 | Partial Inspection | RYAN SALAZAR |
| Final | 4/12/2022 | Permit Finaled | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 4/12/2022 | Approved | ANDREW NAVE |