8837 N WOODLEY AVE 91343
Certificate Information: 8837 N WOODLEY AVE 91343
- Application / Permit
- 21016-20000-18521
- Plan Check / Job No.
- B21VN09354
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) 408 SQ. FT. ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 7/29/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 8/18/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 8/18/2021 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 8/19/2021 | APPLICANT |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | RAUL OLAGI |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/8/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/20/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 12/20/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/28/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 12/28/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 12/28/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 12/28/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 12/28/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 12/28/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 12/28/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 1/3/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 1/3/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 1/3/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 1/3/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/12/2023 | Approved | RAUL OLAGI |
| Insulation | 1/12/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 1/12/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 1/18/2023 | Approved | RAUL OLAGI |
| Final | 2/22/2023 | Conditional Approval | JACK KARGODORIAN |
| Green Building Final | 2/22/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 2/22/2023 | Approved | JACK KARGODORIAN |
| Final | 2/23/2023 | OK to Issue CofO | RAUL OLAGI |