10817 N TELFAIR AVE 91331
Certificate Information: 10817 N TELFAIR AVE 91331
- Application / Permit
- 21016-20000-18444
- Plan Check / Job No.
- B21VN09318
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 42' X 25' REC. ROOM AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 9/14/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | JESSE ARELLANO |
| Corrections Issued | 7/29/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/8/2021 | JESSE ARELLANO |
| Issued | 9/14/2021 | APPLICANT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| CofO in Progress | 12/10/2021 | MICHEL ABAJAN |
| Permit Finaled | 12/28/2021 | MICHAEL SMITH |
| CofO Issued | 12/28/2021 | MICHAEL SMITH |
| Permit Finaled | 12/28/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/20/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2021 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 9/8/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2021 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/5/2021 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/5/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/5/2021 | Approved | MICHEL ABAJAN |
| Insulation | 11/5/2021 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 11/5/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/5/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/22/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Approval | MICHEL ABAJAN |
| Insulation | 11/22/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/24/2021 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/10/2021 | Approved | MICHEL ABAJAN |
| Final | 12/10/2021 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 12/10/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/10/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/10/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/10/2021 | Approved | MICHEL ABAJAN |