6210 N PEACH AVE 91411
Certificate Information: 6210 N PEACH AVE 91411
- Application / Permit
- 21016-20000-18372
- Plan Check / Job No.
- B21VN09291
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1 STORY EXISTING GARAGE CONVERSION TO ADU
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2021 | JOE VO |
| Corrections Issued | 7/21/2021 | JOE VO |
| Plan Check Approved | 7/29/2021 | JOE VO |
| Issued | 10/5/2021 | APPLICANT |
| CofO in Progress | 8/23/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/26/2022 | DANIEL ORRANTE |
| CofO Issued | 8/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/23/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/3/2021 | No Access for Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 12/9/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/9/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/25/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 1/25/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 2/7/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 2/7/2022 | Corrections Issued | ALAN MORELOS |
| Sewer | 2/7/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 3/16/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 3/16/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/23/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 4/18/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 4/22/2022 | Approved | ALAN MORELOS |
| Shower Pan | 4/22/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 4/27/2022 | Approved | ASHLEY THOMPSON |
| Final | 7/21/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 7/21/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 7/21/2022 | Approved | RICHARD DOCKUS |
| Final | 8/5/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 8/10/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/23/2022 | OK to Issue CofO | RICHARD DOCKUS |