10331 N SCOVILLE AVE 91040
Certificate Information: 10331 N SCOVILLE AVE 91040
- Application / Permit
- 21016-20000-18371
- Plan Check / Job No.
- B21VN09289
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan Check* CONVER EXISTING GARAGE TO ADU PER GCS 65852.2(e)(1)(A) AND PER WFPP
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 7/21/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/19/2021 | CRYSTEL MAALOUF |
| Issued | 8/24/2021 | APPLICANT |
| CofO in Progress | 2/17/2023 | DAVID ANDERSON |
| Permit Finaled | 3/21/2023 | MICHAEL SMITH |
| CofO Issued | 3/21/2023 | MICHAEL SMITH |
| Permit Finaled | 3/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/31/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/23/2021 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 9/23/2021 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/27/2021 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/27/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/27/2021 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 10/27/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 10/27/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/2/2021 | Approved | WILLIAM KUEHN |
| Insulation | 11/18/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/18/2021 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 1/6/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 1/13/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 2/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 2/15/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/15/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/15/2023 | Approved | DAVID ANDERSON |
| HVAC-Final | 2/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Final | 2/15/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 2/15/2023 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 2/15/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/16/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 2/16/2023 | Approved | DAVID ANDERSON |
| Final | 2/16/2023 | OK to Issue CofO | DAVID ANDERSON |
| HVAC-Final | 2/16/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 2/16/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | DAVID ANDERSON |