16945-16947 W KNAPP ST 91343
Certificate Information: 16945-16947 W KNAPP ST 91343
- Application / Permit
- 21016-20000-18303
- Plan Check / Job No.
- B21VN09241
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/7/2021
- Issuing Office
- Current Status
- CofO Issued on 5/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | KEVIN MORALES |
| Corrections Issued | 7/22/2021 | KEVIN MORALES |
| Plan Check Approved | 8/28/2021 | KEVIN MORALES |
| Issued | 9/7/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | RAUL OLAGI |
| CofO Issued | 5/26/2022 | MICHAEL SMITH |
| Permit Finaled | 5/26/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/26/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 8/28/2021 | KEVIN MORALES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/20/2021 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 11/15/2021 | Not Ready for Inspection | RAUL OLAGI |
| Pre-Inspection | 1/7/2022 | Partial Inspection | MARK JOHNSON |
| Deputy Drilled-In Anchors | 1/11/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/12/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 1/12/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/14/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/26/2022 | Partial Inspection | RAUL OLAGI |
| Wood Frame | 1/26/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 2/14/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 2/14/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 2/14/2022 | Corrections Issued | RAUL OLAGI |
| Wood Frame | 2/14/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 2/22/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/22/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/22/2022 | Approved | RAUL OLAGI |
| Wood Frame | 2/22/2022 | Corrections Issued | RAUL OLAGI |
| Insulation | 3/1/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 3/1/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 3/7/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/7/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 3/30/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/30/2022 | Approved | RAUL OLAGI |
| Final | 3/30/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 3/30/2022 | Approved | RAUL OLAGI |
| Final | 5/2/2022 | Corrections Issued | RAUL OLAGI |
| Final | 5/25/2022 | OK to Issue CofO | RAUL OLAGI |