2229 S LONGWOOD AVE 90016

Certificate Information: 2229 S LONGWOOD AVE 90016

Application / Permit
21016-20000-18299
Plan Check / Job No.
B21VN09237
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF DETACHED (E) 18'-0" x 18'-0" GARAGE INTO A (N) ADU PER WFPP. ALL WORK TO COMPLY WITH GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 4/4/2022
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/19/2021 ALFRED RAMIREZ
Corrections Issued 7/19/2021 ALFRED RAMIREZ
Plan Check Approved 4/4/2022 ALFRED RAMIREZ
Issued 4/4/2022 APPLICANT
Building Plans Picked Up 4/5/2022 APPLICANT
CofO in Progress 10/27/2023 CALEB MEISTER
Permit Finaled 11/3/2023 DEROLD HAUFF
CofO Issued 11/3/2023 DEROLD HAUFF
Permit Finaled 11/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/3/2021 STEVE MELGAR
Sewer availability Cleared 8/3/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/4/2021 STEVE MELGAR

Contact Information

Contractor United Builders & Development Inc; Lic. No.: 1066908-B 25350 MAGIC MOUNTAIN PARKWAY   STE #300    VALENCIA, CA 91355
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/2/2022 Corrections Issued STUART CHAPMAN
Gas Test 5/2/2022 Partial Approval STUART CHAPMAN
Green Building Rough 5/2/2022 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 5/2/2022 Approved STUART CHAPMAN
PLUMBING-Rough 5/2/2022 Approved STUART CHAPMAN
Sewer 5/2/2022 Approved STUART CHAPMAN
Underground Mechanical 5/2/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 5/10/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/10/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/10/2022 Approved STUART CHAPMAN
Green Building Rough 5/10/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 5/10/2022 Approved STUART CHAPMAN
Insulation 5/16/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/16/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 5/19/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 5/19/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 5/19/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/2/2022 Approved STUART CHAPMAN
Underground Mechanical 6/2/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 8/3/2022 Approved STUART CHAPMAN
Drywall Nailing 8/3/2022 Approved STUART CHAPMAN
Final 8/3/2022 Corrections Issued STUART CHAPMAN
Green Building Final 8/3/2022 Approved STUART CHAPMAN
Green Building Rough 8/3/2022 Approved STUART CHAPMAN
MERV13>=Final 8/3/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/3/2022 Approved STUART CHAPMAN
Final 8/22/2022 Not Ready for Inspection STUART CHAPMAN
Final 10/27/2023 OK to Issue CofO CALEB MEISTER