5807-5809 N ALCOVE AVE 91607

Certificate Information: 5807-5809 N ALCOVE AVE 91607

Application / Permit
21016-20000-18196
Plan Check / Job No.
B21VN09187
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
CONVERT THE (E) ATTACHED GARAGE INTO A (364 S.F) JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22. SEE COMMENTS.
Permit Issued
Issued on 12/18/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 SARKIS HARABEDIAN
Corrections Issued 9/6/2021 SARKIS HARABEDIAN
Plan Check Approved 11/26/2021 SARKIS HARABEDIAN
Building Plans Picked Up 11/29/2021 APPLICANT
Issued 12/18/2021 APPLICANT
CofO in Progress 2/17/2023 DAVID ANDERSON
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/14/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/14/2021 GABRIEL ROBLES
Sewer availability Cleared 10/14/2021 GABRIEL ROBLES

Contact Information

Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/30/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/30/2021 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 1/3/2022 Conditional Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/3/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/3/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/3/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/3/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/3/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 4/5/2022 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 4/29/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/6/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/6/2022 Approved CHRISTOPHE COCHRAN
Insulation 5/13/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 5/23/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 11/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 11/14/2022 Approved CHRISTOPHER DELLEFIELD
Final 11/29/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/29/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 12/13/2022 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 12/13/2022 Not Ready for Inspection ARAM AVEDISIAN
Final 12/23/2022 Not Ready for Inspection DAVID ANDERSON
Green Building Final 12/23/2022 Approved DAVID ANDERSON
Final 2/17/2023 OK to Issue CofO DAVID ANDERSON