15244 W LEMARSH ST 91345
Certificate Information: 15244 W LEMARSH ST 91345
- Application / Permit
- 21016-20000-18087
- Plan Check / Job No.
- B21VN09126
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). (E) GARAGE TO REMAIN.
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | SERGIO MUNIZ |
| Corrections Issued | 7/14/2021 | SERGIO MUNIZ |
| Plan Check Approved | 10/25/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| Issued | 12/15/2021 | APPLICANT |
| CofO in Progress | 11/28/2022 | JENNIFER RABUCHIN |
| CofO Issued | 11/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 10/19/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 4/4/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 4/4/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 4/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 5/4/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 5/16/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/16/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 5/25/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/31/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 8/4/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 8/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/4/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 8/4/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/31/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/31/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/31/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/31/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/31/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Approved | JENNIFER RABUCHIN |