418 1/4 E GAGE AVE 90003

Certificate Information: 418 1/4 E GAGE AVE 90003

Application / Permit
21016-20000-17918
Plan Check / Job No.
B21VN09011
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage into an ADU
Permit Issued
Issued on 8/30/2021
Issuing Office
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/14/2021 JOE VO
Corrections Issued 7/14/2021 JOE VO
Applicant returned to address corrections 7/27/2021 JOE VO
Plan Check Approved 7/30/2021 JOE VO
Issued 8/30/2021 APPLICANT
CofO in Progress 5/21/2022 HORACE FULTZ
Permit Finaled 5/24/2022 DEROLD HAUFF
CofO Issued 5/24/2022 DEROLD HAUFF
Permit Finaled 5/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/26/2021 CELINA MORENO
Sewer availability Cleared 7/26/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/30/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/2/2021 Conditional Approval ALAN MORELOS
Excavation/Setback/Form/Re-Bar 9/2/2021 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/7/2021 Approved DAVID FEILER
Special/Order Compliance 9/7/2021 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 10/8/2021 Partial Approval ADAM ESCOTO
ELECTRICAL-Rough 10/8/2021 Approved ADAM ESCOTO
Green Building Rough 10/8/2021 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 10/8/2021 Partial Approval ADAM ESCOTO
PLUMBING-Rough 10/8/2021 Corrections Issued ADAM ESCOTO
BUILDING-Rough-Frame 10/13/2021 Approved JOHN KLARIN
Green Building Rough 10/13/2021 Approved JOHN KLARIN
HVAC-Rough 10/13/2021 Approved JOHN KLARIN
Insulation 10/13/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 10/13/2021 Approved JOHN KLARIN
PLUMBING-Rough 10/13/2021 Approved JOHN KLARIN
Drywall Nailing 10/19/2021 Approved HORACE FULTZ
ELECTRICAL-Final 5/3/2022 Corrections Issued SABAS ALONSO
Final 5/3/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 5/3/2022 Corrections Issued SABAS ALONSO
HVAC-Final 5/3/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 5/3/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 5/3/2022 Approved SABAS ALONSO
ELECTRICAL-Final 5/10/2022 Approved SABAS ALONSO
Final 5/10/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 5/10/2022 Approved SABAS ALONSO
HVAC-Final 5/10/2022 Approved SABAS ALONSO
PLUMBING-Final 5/10/2022 Approved SABAS ALONSO
Final 5/16/2022 OK to Issue CofO SABAS ALONSO