461 N ALTA VISTA BLVD 90036

Certificate Information: 461 N ALTA VISTA BLVD 90036

Application / Permit
21016-20000-17906
Plan Check / Job No.
B21VN08998
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/2/2021
Issuing Office
Current Status
CofO Issued on 10/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 SELLA BENYAMIN
Corrections Issued 8/2/2021 SELLA BENYAMIN
Quality Review Completed 8/5/2021 OMID HEDAYAT
Building Plans Picked Up 8/18/2021 APPLICANT
Applicant returned to address corrections 8/31/2021 SELLA BENYAMIN
Plan Check Approved 11/2/2021 SELLA BENYAMIN
Issued 11/2/2021 APPLICANT
CofO in Progress 10/19/2023 LILIANA PORTILLO
Permit Finaled 10/29/2023 DEROLD HAUFF
CofO Issued 10/29/2023 DEROLD HAUFF
Permit Finaled 10/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2021 WALLIE JONG
Sewer availability Cleared 11/1/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/2/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Inspection 2/8/2022 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/1/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 3/1/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/29/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 8/29/2022 Approved MICHAEL LEWIS
HVAC-Rough 9/1/2022 Approved MICHAEL LEWIS
Shower Pan 9/1/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/30/2022 Approved MICHAEL LEWIS
Green Building Rough 9/30/2022 Approved MICHAEL LEWIS
METHANE-Rough 9/30/2022 Approved MICHAEL LEWIS
Insulation 10/28/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/28/2022 Approved MICHAEL LEWIS
Drywall Nailing 11/9/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/9/2022 Approved MICHAEL LEWIS
Verify Rec and Parks Fee Memo 8/22/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/12/2023 Approved LILIANA PORTILLO
Final 10/12/2023 Corrections Issued LILIANA PORTILLO
Gas Test 10/12/2023 Approved LILIANA PORTILLO
Green Building Final 10/12/2023 Approved LILIANA PORTILLO
HVAC-Final 10/12/2023 Approved LILIANA PORTILLO
PLUMBING-Final 10/12/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 10/12/2023 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 10/12/2023 Approved LILIANA PORTILLO
Final 10/17/2023 Corrections Issued SCOTT FINNILA
Service/Power Release 10/17/2023 Approved SCOTT FINNILA
Final 10/19/2023 OK to Issue CofO LILIANA PORTILLO