428 N GREENCRAIG ROAD 90049
Certificate Information: 428 N GREENCRAIG ROAD 90049
- Application / Permit
- 21016-20000-17809
- Plan Check / Job No.
- B21VN08957
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, ADD & EXPAND ( 25'-9"x 14'-6") EXISTING RAISED DECKING AT REAR, ADD (10'x 7') 70 SF SHOWER ROOM @ GRADE OF (E) SINGLE FAMILY DWELLING AND ADD NEW SKYLIGHT. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- Issued on 3/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | TROY DEGUZMAN |
| Corrections Issued | 8/22/2021 | TROY DEGUZMAN |
| Quality Review Completed | 8/24/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/27/2021 | APPLICANT |
| Applicant returned to address corrections | 12/1/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/1/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/16/2022 | TROY DEGUZMAN |
| Issued | 3/17/2022 | APPLICANT |
Permit Application Clearance Information
| Watercourse | Cleared | 9/10/2021 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | MAHELET GEBEYHU |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 3/1/2022 | VASIL MIHALEV |
| Green Code | Cleared | 3/1/2022 | VASIL MIHALEV |
| Miscellaneous | Cleared | 3/10/2022 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/21/2022 | Partial Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/6/2022 | Approved | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/25/2022 | Conditional Approval | JUAN VALENZUELA |
| Deck | 4/28/2022 | Approved | JUAN VALENZUELA |
| Wood Frame | 4/28/2022 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/13/2022 | Approved | JUAN VALENZUELA |
| Wood Frame | 3/8/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/11/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 6/11/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 6/11/2024 | Not Ready for Inspection | KEVIN SARGSYAN |