20159 W RINALDI ST STE. 100 91326
Certificate Information: 20159 W RINALDI ST STE. 100 91326
- Application / Permit
- 21016-20000-17777
- Plan Check / Job No.
- B21VN08934
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- CHANGE OF USE FROM BANK TO RETAIL STORE.
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | JOE VO |
| Corrections Issued | 7/12/2021 | JOE VO |
| Plan Check Approved | 8/6/2021 | JOE VO |
| Issued | 8/18/2021 | APPLICANT |
| CofO in Progress | 1/7/2022 | JEFFREY FULTON |
| CofO Issued | 1/7/2022 | JEFFREY DURAN |
| Permit Finaled | 1/7/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Brockman,, Patrick Carl; Lic. No.: C21492 | W8088 OLD CTH NA HOLMEN, WI 54636 |
| Contractor | Tetras Construction Corporation; Lic. No.: 617073-B | 4095 E LA PALMA AVE STE E ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 10/27/2021 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Approved | JEFFREY FULTON |
| Drywall Nailing | 11/4/2021 | Corrections Issued | JEFFREY FULTON |
| Light Gage Steel Frame | 11/9/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 11/15/2021 | Partial Inspection | JONATHAN QUACH |
| T-Bar Ceiling | 11/18/2021 | Partial Inspection | JEFFREY FULTON |
| Final | 12/21/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 12/21/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 12/21/2021 | Approved | JEFFREY FULTON |
| Final | 12/23/2021 | Off-Hour Fees Due | |
| Wood Frame | 12/23/2021 | Off-Hour Fees Due | |
| Final | 12/27/2021 | OK to Issue CofO | JEFFREY FULTON |
| Wood Frame | 12/27/2021 | Approved | JEFFREY FULTON |