1411-1411 1/2 E 21ST ST 90011

Certificate Information: 1411-1411 1/2 E 21ST ST 90011

Application / Permit
21016-20000-17741
Plan Check / Job No.
B21VN08913
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN Convert 663 sf portion of existing SFD into Attached ADU Per Ordinance and LAMC 12.22 A 33(c) (e).
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 3/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/10/2021 ZAW HAN
Corrections Issued 8/11/2021 ZAW HAN
Applicant returned to address corrections 8/31/2021 ZAW HAN
Plan Check Approved 9/16/2021 ZAW HAN
Issued 10/5/2021 APPLICANT
CofO in Progress 3/9/2022 AMY COLIN
Permit Finaled 3/18/2022 DEROLD HAUFF
CofO Issued 3/18/2022 DEROLD HAUFF
Permit Finaled 3/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/3/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 9/3/2021 THOMAS LANG
Sewer availability Cleared 9/3/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/10/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Gurrola,, Suzuki; Lic. No.: C81001 22814 ASH CREEK LN      SANTA CLARITA, CA 91354

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/18/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 11/18/2021 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 11/18/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 11/23/2021 Conditional Approval JOAQUIN GREENOUGH
Wood Frame 11/23/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 12/1/2021 Partial Approval JOAQUIN GREENOUGH
Insulation 12/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Shower Pan 12/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 12/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 12/10/2021 Partial Approval JOAQUIN GREENOUGH
Wood Frame 12/10/2021 Approved JOAQUIN GREENOUGH
Drywall Nailing 12/17/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/17/2021 Approved LILIANA PORTILLO
Drywall Nailing 12/22/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 12/22/2021 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/28/2022 Corrections Issued HORACE FULTZ
Final 2/28/2022 Corrections Issued HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved HORACE FULTZ
Smoke Detectors 2/28/2022 Corrections Issued HORACE FULTZ
BUILDING-Rough-Frame 3/8/2022 Approved AMY COLIN
ELECTRICAL-Final 3/8/2022 Approved AMY COLIN
Final 3/8/2022 OK to Issue CofO AMY COLIN
HVAC-Final 3/8/2022 Approved AMY COLIN
PLUMBING-Final 3/8/2022 Approved AMY COLIN
Smoke Detectors 3/8/2022 Approved AMY COLIN