7919 N JAMIESON AVE 91335

Certificate Information: 7919 N JAMIESON AVE 91335

Application / Permit
21016-20000-17707
Plan Check / Job No.
B21VN08901
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-0" X 12'-0" ADDITION TO (E) SFD AND INTTERIOR REMODEL TO (E) BEDROOM. "COMPLY WITH DEPARTMENT ORDER effective date 03/24/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/21/2021 OMAR GARNICA
Corrections Issued 7/21/2021 OMAR GARNICA
Building Plans Picked Up 9/13/2021 APPLICANT
Plan Check Approved 9/27/2021 OMAR GARNICA
Issued 10/26/2021 APPLICANT
CofO in Progress 12/4/2024 JONATHAN FRANCHINI
Permit Finaled 10/7/2025 DANIEL SANCHEZ
CofO Issued 10/7/2025 DANIEL SANCHEZ
Permit Finaled 10/7/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/25/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/27/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2022 No Access for Inspection MARK DOVICO
Pre-Inspection 12/6/2022 Approved MARK DOVICO
Pre-Inspection 10/25/2023 Approved ARAM AVAKIAN
BUILDING-Rough-Frame 9/20/2024 No Access for Inspection JONATHAN FRANCHINI
Footing/Foundation/Slab 9/20/2024 No Access for Inspection JONATHAN FRANCHINI
Green Building Rough 9/20/2024 No Access for Inspection JONATHAN FRANCHINI
BUILDING-Rough-Frame 10/23/2024 Not Ready for Inspection JONATHAN FRANCHINI
Footing/Foundation/Slab 10/23/2024 Approved JONATHAN FRANCHINI
Green Building Rough 10/23/2024 Not Ready for Inspection JONATHAN FRANCHINI
Wood Frame 10/23/2024 Not Ready for Inspection JONATHAN FRANCHINI
Wood Frame 11/5/2024 Conditional Approval JONATHAN FRANCHINI
BUILDING-Rough-Frame 11/15/2024 Approved JONATHAN FRANCHINI
Drywall Nailing 11/15/2024 Approved JONATHAN FRANCHINI
Final 11/15/2024 Not Ready for Inspection JONATHAN FRANCHINI
Green Building Final 11/15/2024 Approved JONATHAN FRANCHINI
Green Building Rough 11/15/2024 Approved JONATHAN FRANCHINI
Insulation 11/15/2024 Approved JONATHAN FRANCHINI
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved JONATHAN FRANCHINI
Smoke Detectors 11/15/2024 Approved JONATHAN FRANCHINI
Interior/Exterior Lathing 11/20/2024 Approved JONATHAN FRANCHINI
Rough-Elec/Plmb/HVAC 11/20/2024 Approved JONATHAN FRANCHINI
ELECTRICAL-Final 12/3/2024 Approved JONATHAN FRANCHINI
Final 12/3/2024 OK to Issue CofO JONATHAN FRANCHINI
HVAC-Final 12/3/2024 Approved JONATHAN FRANCHINI
PLUMBING-Final 12/3/2024 Approved JONATHAN FRANCHINI