7041 N LUBAO AVE 91306
Certificate Information: 7041 N LUBAO AVE 91306
- Application / Permit
- 21016-20000-17652
- Plan Check / Job No.
- B21VN08857
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' 3" X 18' 4" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/24/2021
- Issuing Office
- Current Status
- CofO Issued on 6/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 7/12/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/23/2021 | GURUNATH NESARAJAH |
| Issued | 10/24/2021 | APPLICANT |
| Building Plans Picked Up | 10/25/2021 | APPLICANT |
| CofO in Progress | 6/6/2022 | STEVEN BACK |
| Permit Finaled | 6/7/2022 | JOHN JANSON |
| CofO Issued | 6/7/2022 | JOHN JANSON |
| Permit Finaled | 6/7/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/22/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2021 | GABRIEL ROBLES |
| ZI | Cleared | 7/27/2021 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 9/30/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/13/2022 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 1/27/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 1/27/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 2/8/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 2/8/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 2/8/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 2/16/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 2/16/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 2/16/2022 | Approved | STEVEN BACK |
| Insulation | 2/16/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 2/16/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 2/17/2022 | Approved | STEVEN BACK |
| Insulation | 2/17/2022 | Approved | STEVEN BACK |
| Shower Pan | 2/17/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 2/24/2022 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/24/2022 | Approved | JAVIER RAMOS JR |
| Sewer | 2/24/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/24/2022 | Approved | JAVIER RAMOS JR |
| Final | 5/17/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 5/17/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 5/17/2022 | Approved | STEVEN BACK |
| Final | 6/6/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | STEVEN BACK |