5644-5646 N OSO AVE 91367
Certificate Information: 5644-5646 N OSO AVE 91367
- Application / Permit
- 21016-20000-17375
- Plan Check / Job No.
- B21VN08705
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (405 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 9/11/2021
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 7/20/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/30/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| Issued | 9/11/2021 | APPLICANT |
| CofO in Progress | 1/19/2023 | ALEXANDER HANDY |
| CofO Issued | 1/25/2023 | JOHN JANSON |
| Permit Finaled | 1/25/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/5/2021 | GABRIEL ROBLES |
| ZA Case | Cleared | 8/5/2021 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 8/19/2021 | TIMOTHY POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/29/2021 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 10/29/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 11/8/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 1/3/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 1/3/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 1/3/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 1/5/2022 | Approved | JEFFREY PARD |
| Sewer | 1/5/2022 | Approved | JEFFREY PARD |
| Wood Frame | 1/5/2022 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 1/7/2022 | Approved | STEVEN BACK |
| Green Building Rough | 1/7/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 1/18/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 1/18/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 1/18/2022 | Approved | STEVEN BACK |
| Shower Pan | 1/18/2022 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 1/20/2022 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/20/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 1/20/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 1/20/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 1/20/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 1/25/2022 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Rough | 1/28/2022 | Approved | STEVEN BACK |
| Insulation | 1/28/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 2/3/2022 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/14/2022 | Approved | STEVEN BACK |
| Final | 3/14/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/14/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 3/14/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 3/14/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/14/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 1/11/2023 | Approved | ALEXANDER HANDY |
| Final | 1/11/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 1/11/2023 | Approved | ALEXANDER HANDY |
| HVAC-Final | 1/11/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/11/2023 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/11/2023 | Approved | ALEXANDER HANDY |
| Final | 1/18/2023 | OK to Issue CofO | ALEXANDER HANDY |