12512 W VICTORY BLVD STE A 91606
Certificate Information: 12512 W VICTORY BLVD STE A 91606
- Application / Permit
- 21016-20000-17196
- Plan Check / Job No.
- B21VN08590
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Clinic
- Work Description
- PROPOSED NONSTRUCT INT T.I. AND CHANGE OF USE FROM RETAIL TO MEDICAL CLINIC WITH OFFICES. (NOT OSHPD 3 PROJECT). SEE COMMENTS.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 8/9/2021 | HAYATO TSUCHIYA |
| Quality Review Completed | 8/13/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/19/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/30/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Issued | 12/3/2021 | APPLICANT |
| CofO in Progress | 2/27/2024 | ROBERT DAVIS |
| Permit Finaled | 3/6/2024 | JEFFREY DURAN |
| CofO Issued | 3/6/2024 | JEFFREY DURAN |
| Permit Finaled | 3/6/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/11/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 8/11/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/12/2021 | GABRIEL ROBLES |
| Comm Cor/Mini-Mall | Cleared | 10/22/2021 | LAUREN PADICK |
| DAS Clearance | Cleared | 11/24/2021 | HAYATO TSUCHIYA |
Contact Information
| Contractor | Bravo Builders; Lic. No.: 1073185-B | 6527 VALMONT ST TUJUNGA, CA 91042 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/8/2022 | Corrections Issued | ROBERT DAVIS |
| Pre-Inspection | 2/18/2022 | Corrections Issued | ROBERT DAVIS |
| Drywall Nailing | 4/6/2022 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 4/6/2022 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 4/8/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/5/2022 | Corrections Issued | ROBERT DAVIS |
| Light Gage Steel Frame | 11/1/2022 | Approved | ROBERT DAVIS |
| Drywall Nailing | 11/9/2022 | Approved | DANIEL VARNUM |
| Final | 7/11/2023 | Corrections Issued | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 7/11/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 7/11/2023 | Approved | ROBERT DAVIS |
| Final | 8/3/2023 | OK to Issue CofO | ROBERT DAVIS |
| Special/Order Compliance | 1/18/2024 | Partial Inspection | ROBERT DAVIS |
| Special/Order Compliance | 1/24/2024 | Partial Inspection | ROBERT DAVIS |