21044-21046 W COVELLO ST 91303
Certificate Information: 21044-21046 W COVELLO ST 91303
- Application / Permit
- 21016-20000-17092
- Plan Check / Job No.
- B21VN08521
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 18' X 19'-6" ATTACHED GARAGE AND CONVERT 10'-10" X 14'-8" IRREGULAR SHAPED PORTION OF (E) SFD TO JUNIOR ACCESORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 3/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/12/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 8/13/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/16/2021 | APPLICANT |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 3/30/2022 | STEVEN BACK |
| Permit Finaled | 3/30/2022 | JOHN JANSON |
| CofO Issued | 3/30/2022 | JOHN JANSON |
| Permit Finaled | 3/30/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2021 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 9/22/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 9/22/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 9/22/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 11/4/2021 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 11/4/2021 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 12/7/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | STEVEN BACK |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 12/7/2021 | Corrections Issued | STEVEN BACK |
| Shower Pan | 12/7/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 1/4/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 1/4/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 1/4/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 1/10/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 1/10/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 1/24/2022 | Approved | STEVEN BACK |
| Green Building Rough | 1/24/2022 | Approved | STEVEN BACK |
| Insulation | 1/24/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 2/9/2022 | Approved | MORRIS JACKSON |
| Final | 3/29/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 3/29/2022 | Approved | STEVEN BACK |
| HVAC-Final | 3/29/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 3/29/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/29/2022 | Approved | STEVEN BACK |