10745 W TABOR ST 90034
Certificate Information: 10745 W TABOR ST 90034
- Application / Permit
- 21016-20000-17057
- Plan Check / Job No.
- B21VN08499
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE PORTION OF (E) ATTACHED GARAGE AND CONVERT TO (N) CARPORT, REMODEL THROUGHOUT (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | JENNIFER LEE |
| Corrections Issued | 7/1/2021 | JENNIFER LEE |
| Plan Check Approved | 7/14/2021 | JENNIFER LEE |
| Issued | 7/14/2021 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 4/4/2022 | EVAN COOPER |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
| CofO Issued | 4/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/14/2021 | JENNIFER LEE |
Contact Information
| Contractor | Dream Remodeling Inc; Lic. No.: 889254-B | 22704 VENTURA BLVD #444 WOODLAND HILLS, CA 91411 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/17/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 8/17/2021 | Corrections Issued | JUAN VALENZUELA |
| Wood Frame | 8/17/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 8/31/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/31/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/14/2021 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 10/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 10/19/2021 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 10/22/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 10/25/2021 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 10/28/2021 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | JOHNNY MIRANDA |
| Wood Frame | 11/8/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/12/2021 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/9/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 2/9/2022 | Approved | JOHNNY MIRANDA |
| Final | 2/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| Smoke Detectors | 2/9/2022 | Approved | JOHNNY MIRANDA |
| Final | 2/15/2022 | Corrections Issued | JOHNNY MIRANDA |
| Final | 4/4/2022 | OK to Issue CofO | EVAN COOPER |