8110 N WOODMAN AVE 91402
Certificate Information: 8110 N WOODMAN AVE 91402
- Application / Permit
- 21016-20000-16944
- Plan Check / Job No.
- B21VN08440
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Clinic
- Work Description
- *ePLAN CHECK* TENANT IMPROVEMENT TO (E) MEDICAL CLINIC FOR REPLACEMENT OF MAMMOGRAPHY SYSTEM ANCHORAGE
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/18/2023
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | LAMAR DAVIS |
| Corrections Issued | 8/9/2021 | LAMAR DAVIS |
| Quality Review Completed | 8/10/2021 | PRANITA SHAH |
| Plan Check Approved | 8/20/2021 | LAMAR DAVIS |
| Issued | 9/1/2021 | APPLICANT |
| Permit Finaled | 10/18/2023 | KENNETH ROBERTS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B | 4175 E LA PALMA AVE STE 200 ANAHEIM, CA 92807 |
| Engineer | Sangiovanni,, Ricardo Jorge; Lic. No.: NA5001 | , |
| Engineer | Sangiovanni,, Ricardo Jorge; Lic. No.: S5001 | 808 MILLARD CANYON RD ALTADENA, CA 91001 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/9/2023 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 1/26/2023 | Partial Inspection | ANDREW DORSO |
| Special/Order Compliance | 1/26/2023 | Partial Approval | STEVEN LEVITT |
| Drywall Nailing | 1/27/2023 | Partial Inspection | ANDREW DORSO |
| Special/Order Compliance | 1/27/2023 | Partial Approval | STEVEN LEVITT |
| Drywall Nailing | 1/30/2023 | Partial Inspection | ANDREW DORSO |
| Final | 3/1/2023 | Partial Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 3/1/2023 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 4/24/2023 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/27/2023 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 5/18/2023 | Conditional Approval | ANDREW DORSO |
| Final | 6/2/2023 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/26/2023 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/27/2023 | Partial Inspection | ANDREW DORSO |
| Final | 7/31/2023 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 9/21/2023 | Approved | ANDREW DORSO |
| Drywall Nailing | 9/22/2023 | Approved | ANDREW DORSO |
| Deputy Drilled-In Anchors | 10/10/2023 | Conditional Approval | JEFFREY DURAN |
| Final | 10/18/2023 | Permit Finaled | KENNETH ROBERTS |