5932 N VESPER AVE 91411
Certificate Information: 5932 N VESPER AVE 91411
- Application / Permit
- 21016-20000-16942
- Plan Check / Job No.
- B21VN08434
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 15'-11" X 24'-5" 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/4/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/7/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 10/22/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 2/8/2024 | RYAN SALAZAR |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
| CofO Issued | 4/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/5/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/12/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 9/28/2021 | JOHN BACON |
| Hydrant and Access approval | Cleared | 10/9/2021 | GILBERT URREA |
| Public Works-Highway Ded. | Cleared | 7/5/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 7/5/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 7/5/2022 | MEGAN GODINEZ |
Contact Information
| Architect | Chang,, Monica K; Lic. No.: C37524 | 2214 1/2 W 239TH STREET TORRANCE, CA 90501 |
| Contractor | Koam Construction Inc; Lic. No.: 690788-B | 4329 BRIGGS AVENUE MONTROSE, CA 91020 |
| Engineer | Posadas,, John Garcia; Lic. No.: C30786 | 2063 PASEO LUCINDA SAN DIMAS, CA 91773 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/28/2022 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/4/2022 | No Access for Inspection | MICHEL ABAJAN |
| Underground Mechanical | 10/4/2022 | No Access for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 10/5/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/11/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 12/14/2022 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/3/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/3/2023 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 2/3/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/17/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 2/17/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 2/17/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/28/2023 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 2/28/2023 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 4/3/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 4/3/2023 | Approved | RYAN SALAZAR |
| Insulation | 4/12/2023 | Conditional Approval | JOHN COLEMAN |
| Drywall Nailing | 5/1/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 6/1/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/9/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | JUAN VALENZUELA |
| Final | 11/1/2023 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 11/1/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 11/1/2023 | Not Required | JUAN VALENZUELA |
| Smoke Detectors | 11/1/2023 | Approved | JUAN VALENZUELA |
| Final | 2/7/2024 | OK to Issue CofO | RYAN SALAZAR |