6705 N MCLENNAN AVE 91406

Certificate Information: 6705 N MCLENNAN AVE 91406

Application / Permit
21016-20000-16940
Plan Check / Job No.
B21VN08432
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER DESIGN.
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/2/2021 RAPHAEL ROSAS
Corrections Issued 7/4/2021 RAPHAEL ROSAS
Plan Check Approved 9/29/2021 RAPHAEL ROSAS
Building Plans Picked Up 9/30/2021 APPLICANT
Issued 10/19/2021 APPLICANT
CofO in Progress 3/14/2023 RAUL OLAGI
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/9/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/9/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/9/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 9/20/2021 RIDWAN HARDY

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor N E Construction; Lic. No.: 1042454-B 6399 SMOKE TREE AVE      OAK PARK, CA 91377

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/5/2021 Approved RAUL OLAGI
Gas Test 11/5/2021 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 11/5/2021 Corrections Issued RAUL OLAGI
Underground Mechanical 11/5/2021 Corrections Issued RAUL OLAGI
Gas Test 11/16/2021 Approved RAUL OLAGI
PLUMBING-Rough 11/16/2021 Corrections Issued RAUL OLAGI
Sewer 11/16/2021 Approved RAUL OLAGI
Underground Mechanical 11/16/2021 Approved RAUL OLAGI
Underground Mechanical 11/16/2021 Partial Inspection ALAN MORELOS
ELECTRICAL-Rough 11/18/2021 Approved RAUL OLAGI
PLUMBING-Rough 11/18/2021 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Approved RAUL OLAGI
Green Building Rough 11/23/2021 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 11/29/2021 Approved RAUL OLAGI
Green Building Rough 11/29/2021 Approved RAUL OLAGI
HVAC-Rough 11/29/2021 Partial Approval RAUL OLAGI
Insulation 11/29/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 11/29/2021 Partial Approval RAUL OLAGI
Drywall Nailing 12/8/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 12/8/2021 Approved ALAN MORELOS
Shower Pan 12/8/2021 Approved ALAN MORELOS
ELECTRICAL-Final 2/15/2023 Corrections Issued RAUL OLAGI
Final 2/15/2023 Corrections Issued RAUL OLAGI
Green Building Final 2/15/2023 Approved RAUL OLAGI
HVAC-Final 2/15/2023 Approved RAUL OLAGI
PLUMBING-Final 2/15/2023 Corrections Issued RAUL OLAGI
Smoke Detectors 2/15/2023 Approved RAUL OLAGI
PLUMBING-Final 2/27/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved RAUL OLAGI
ELECTRICAL-Final 3/14/2023 Approved RAUL OLAGI
Final 3/14/2023 OK to Issue CofO RAUL OLAGI