6705 N MCLENNAN AVE 91406
Certificate Information: 6705 N MCLENNAN AVE 91406
- Application / Permit
- 21016-20000-16940
- Plan Check / Job No.
- B21VN08432
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER DESIGN.
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/4/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 9/29/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| Issued | 10/19/2021 | APPLICANT |
| CofO in Progress | 3/14/2023 | RAUL OLAGI |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
| CofO Issued | 4/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/9/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 9/20/2021 | RIDWAN HARDY |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | N E Construction; Lic. No.: 1042454-B | 6399 SMOKE TREE AVE OAK PARK, CA 91377 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/5/2021 | Approved | RAUL OLAGI |
| Gas Test | 11/5/2021 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 11/5/2021 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 11/5/2021 | Corrections Issued | RAUL OLAGI |
| Gas Test | 11/16/2021 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/16/2021 | Corrections Issued | RAUL OLAGI |
| Sewer | 11/16/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/16/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/16/2021 | Partial Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 11/18/2021 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 11/18/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | RAUL OLAGI |
| Green Building Rough | 11/29/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/29/2021 | Partial Approval | RAUL OLAGI |
| Insulation | 11/29/2021 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/29/2021 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 12/8/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 12/8/2021 | Approved | ALAN MORELOS |
| Shower Pan | 12/8/2021 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 2/15/2023 | Corrections Issued | RAUL OLAGI |
| Final | 2/15/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/15/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 2/15/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/15/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 2/15/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/27/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/14/2023 | Approved | RAUL OLAGI |
| Final | 3/14/2023 | OK to Issue CofO | RAUL OLAGI |