5840 W 75TH ST 90045
Certificate Information: 5840 W 75TH ST 90045
- Application / Permit
- 21016-20000-16842
- Plan Check / Job No.
- B21VN08367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel to existing single-family dwelling. Remodel a bedroom, 2 bathrooms, laundry room and kitchen. Install new skylight at kitchen. Remove portion of walls between kitchen and living/dining room. All work per engineer.
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/9/2022
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | ANGELICA DAVE |
| Corrections Issued | 6/30/2021 | ANGELICA DAVE |
| Plan Check Approved | 8/6/2021 | ANGELICA MARTINEZ |
| Issued | 8/6/2021 | APPLICANT |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| Permit Finaled | 4/9/2022 | BOBBY KEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/6/2021 | ANGELICA MARTINEZ |
Contact Information
| Contractor | Yarden Builders Inc; Lic. No.: 952977-B | 17425 CHATSWORTH STREET #101 GRANADA HILLS, CA 91344 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/12/2021 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/12/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/24/2021 | Corrections Issued | BRENDAN LOONEY |
| MERV13>=Rough | 8/24/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/10/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/10/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/17/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/17/2021 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/23/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| MERV13>=Rough | 9/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/28/2021 | Approved | BRENDAN LOONEY |
| MERV13>=Rough | 9/28/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 9/28/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/12/2021 | Corrections Issued | DAVID FEILER |
| MERV13>=Rough | 10/12/2021 | Not Ready for Inspection | DAVID FEILER |
| Drywall Nailing | 10/28/2021 | Not Ready for Inspection | BOBBY KEY |
| Pre-Inspection | 10/28/2021 | Partial Inspection | DAVID FEILER |
| Drywall Nailing | 11/12/2021 | Partial Approval | JOHN KAYON |
| Interior/Exterior Lathing | 11/12/2021 | Corrections Issued | JOHN KAYON |
| Shower Pan | 11/17/2021 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 11/23/2021 | Partial Approval | DEANDRE HOFFMAN |
| Shower Pan | 11/23/2021 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 12/14/2021 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | BOBBY KEY |
| Final | 3/10/2022 | Corrections Issued | BOBBY KEY |
| MERV13>=Final | 3/10/2022 | Approved | BOBBY KEY |
| MERV13>=Rough | 3/10/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/10/2022 | Approved | BOBBY KEY |
| Final | 4/9/2022 | Permit Finaled | BOBBY KEY |