8355 N COSTELLO AVE 91402

Certificate Information: 8355 N COSTELLO AVE 91402

Application / Permit
21016-20000-16591
Plan Check / Job No.
B21VN08266
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ADU WITH A 1-STORY ADDITION TO CREATE A DETACHED ADU PER ORDINANCE
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/29/2021 CARLOS MONTES
Corrections Issued 7/9/2021 CARLOS MONTES
Plan Check Approved 10/13/2021 CARLOS MONTES
Issued 10/19/2021 APPLICANT
CofO in Progress 4/14/2022 DAVID MATSON
Permit Finaled 7/23/2022 MICHAEL SMITH
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/14/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 7/14/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/15/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/15/2021 DAGOVERTO GUERRERO
Construction within easement Cleared 10/7/2021 RIDWAN HARDY

Contact Information

Contractor Carter Design & Remodeling Inc; Lic. No.: 932102-B 23890 COPPERHILL DRIVE #375      VALENCIA, CA 91354

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 11/23/2021 Approved WILLIAM WREN
PLUMBING-Rough 11/23/2021 Partial Approval WILLIAM WREN
Underground Mechanical 12/1/2021 Approved WILLIAM WREN
Deputy Drilled-In Anchors 12/2/2021 Conditional Approval WILLIAM WREN
Footing/Foundation/Slab 12/3/2021 Approved WILLIAM WREN
Sewer 12/15/2021 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 1/12/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/12/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 1/12/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/12/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 1/13/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 1/19/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 1/19/2022 Approved GREGG CUMMINGS
Green Building Rough 1/19/2022 Approved GREGG CUMMINGS
HVAC-Rough 1/19/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 1/19/2022 Approved GREGG CUMMINGS
Insulation 1/24/2022 Approved ASHLEY THOMPSON
Drywall Nailing 1/28/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/28/2022 Partial Approval GREGG CUMMINGS
Sewer 2/14/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 3/3/2022 Not Ready for Inspection GREGG CUMMINGS
Final 3/3/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 3/3/2022 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 3/3/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 3/3/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 3/14/2022 Approved GREGG CUMMINGS
Final 3/14/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 3/14/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 3/14/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 3/21/2022 Not Ready for Inspection GREGG CUMMINGS
Final 3/21/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 3/21/2022 Not Ready for Inspection GREGG CUMMINGS
Service/Power Release 3/21/2022 Not Ready for Inspection GREGG CUMMINGS
Special/Order Compliance 3/21/2022 Not Ready for Inspection GREGG CUMMINGS
Final 4/13/2022 OK to Issue CofO DAVID MATSON