18105 W CHASE ST 91325
Certificate Information: 18105 W CHASE ST 91325
- Application / Permit
- 21016-20000-16521
- Plan Check / Job No.
- B21VN08216
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED TWO CAR GARAGE INTO A (N) 400 SQ. FT. ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | JESSE ARELLANO |
| Corrections Issued | 7/2/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 9/20/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/1/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/13/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| Plan Check Approved | 11/4/2021 | JESSE ARELLANO |
| Issued | 11/15/2021 | APPLICANT |
| CofO in Progress | 6/15/2023 | JOHN KIDWELL |
| Permit Finaled | 6/26/2023 | JOHN JANSON |
| CofO Issued | 6/26/2023 | JOHN JANSON |
| Permit Finaled | 6/26/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 10/1/2021 | JESSE ARELLANO |
Contact Information
| Contractor | R L T Construction; Lic. No.: 485792-B | 8860 CORBIN AVE PMB #148 NORTHRIDGE, CA 91324 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/28/2022 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 4/18/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 4/18/2022 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/26/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 5/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 5/26/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/15/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/29/2022 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 8/29/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 8/29/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 8/29/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/25/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/25/2023 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 1/25/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 1/25/2023 | Approved | DAVID SCANTLIN |
| Insulation | 1/30/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 2/2/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 2/2/2023 | Approved | DAVID SCANTLIN |
| Shower Pan | 2/2/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 4/24/2023 | Approved | DAVID SCANTLIN |
| Final | 4/24/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 4/24/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 4/24/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 4/24/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 4/24/2023 | Approved | DAVID SCANTLIN |
| Green Building Final | 5/24/2023 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Not Required | JOHN KIDWELL |
| Special/Order Compliance | 5/24/2023 | Partial Inspection | MORRIS JACKSON |
| Final | 6/14/2023 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 6/14/2023 | Approved | JOHN KIDWELL |