15514 W BRIARWOOD DR 91403
Certificate Information: 15514 W BRIARWOOD DR 91403
- Application / Permit
- 21016-20000-16504
- Plan Check / Job No.
- B21VN08203
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 2'-5" X 8'-5" PORTION OF (E) GARAGE TO ENLARGE KITCHEN, REMODEL FOYER, KITCHEN AND LAUNDRY ROOM, CONVERT CLOSET TO POWDER ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/29/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/30/2021 | APPLICANT |
| Plan Check Approved | 8/19/2021 | RAPHAEL ROSAS |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 11/18/2021 | JACK KARGODORIAN |
| CofO Issued | 2/12/2022 | MICHAEL SMITH |
| Permit Finaled | 2/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/11/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 9/9/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Wood Frame | 9/9/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/13/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/13/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 9/13/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/13/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/21/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/21/2021 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 9/21/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 9/21/2021 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 9/21/2021 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 9/22/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 9/23/2021 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 9/23/2021 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 9/23/2021 | Partial Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 9/27/2021 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/8/2021 | Corrections Issued | JACK KARGODORIAN |
| MERV13>=Final | 11/8/2021 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 11/8/2021 | Approved | JACK KARGODORIAN |
| Final | 11/18/2021 | OK to Issue CofO | JACK KARGODORIAN |