10558 W AYRES AVE 90064

Certificate Information: 10558 W AYRES AVE 90064

Application / Permit
21016-20000-16406
Plan Check / Job No.
B21VN08146
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 18'3"X18' DET GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481 PER ENGR DESIGN.
Permit Issued
Issued on 10/1/2021
Issuing Office
Current Status
CofO Issued on 10/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 HAYATO TSUCHIYA
Corrections Issued 6/25/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 9/15/2021 PARISA ZAHABI
Plan Check Approved 10/1/2021 HAYATO TSUCHIYA
Issued 10/1/2021 APPLICANT
Building Plans Picked Up 10/5/2021 APPLICANT
CofO in Progress 9/13/2022 STEPHANIE SWANSON
CofO in Progress 9/14/2022 STEPHANIE SWANSON
CofO in Progress 10/21/2022 STEPHANIE SWANSON
Permit Finaled 10/27/2022 DANIEL ORRANTE
CofO Issued 10/27/2022 DANIEL ORRANTE
Permit Finaled 10/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 7/7/2021 WESTON PRINGLE
Address approval Cleared 7/12/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/13/2021 DINAH GARIN
Sewer availability Cleared 7/13/2021 DINAH GARIN
Construction near power lines Cleared 8/31/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/15/2021 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/6/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 12/13/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/20/2022 Corrections Issued KEVIN SARGSYAN
Deputy Drilled-In Anchors 1/26/2022 No Result Entered RONALD WEBER
Footing/Foundation/Slab 1/31/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 2/14/2022 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 3/4/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 3/4/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 3/4/2022 Corrections Issued KEVIN SARGSYAN
Sewer 3/4/2022 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 3/9/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 3/9/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/18/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval KEVIN SARGSYAN
HVAC-Rough 3/18/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval KRISTEN CAUSEY
Insulation 3/30/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 3/30/2022 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 4/7/2022 Approved KEVIN SARGSYAN
Drywall Nailing 4/7/2022 Approved KEVIN SARGSYAN
Green Building Rough 4/7/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/7/2022 Approved KEVIN SARGSYAN
Final 6/3/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 6/3/2022 Approved KEVIN SARGSYAN
METHANE-Final 6/3/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 6/3/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/5/2022 Approved KEVIN SARGSYAN
Final 7/5/2022 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 7/5/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 7/5/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved KEVIN SARGSYAN
Final 9/13/2022 Conditional Approval STEPHANIE SWANSON
Final 9/13/2022 Corrections Issued STEPHANIE SWANSON
Final 9/14/2022 Corrections Issued STEPHANIE SWANSON
Final 10/21/2022 OK to Issue CofO STEPHANIE SWANSON