14931 W CHATSWORTH ST 91345

Certificate Information: 14931 W CHATSWORTH ST 91345

Application / Permit
21016-20000-16113
Plan Check / Job No.
B21VN07978
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 8/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 6/23/2021 CARLOS MONTES
Corrections Issued 6/23/2021 CARLOS MONTES
Applicant returned to address corrections 7/2/2021 CARLOS MONTES
Applicant returned to address corrections 7/13/2021 CARLOS MONTES
Plan Check Approved 7/27/2021 CARLOS MONTES
Issued 8/31/2021 APPLICANT
CofO in Progress 4/14/2024 JENNIFER RABUCHIN
Permit Finaled 8/7/2024 RUBEN SALAS
Permit Finaled 8/7/2024 RUBEN SALAS
CofO Issued 8/7/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/25/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/25/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/25/2021 ADRIAN CASTRO
Sewer availability Cleared 6/25/2021 ADRIAN CASTRO

Contact Information

Contractor Gonzalez Juan; Lic. No.: 1010495-B 400 FOREST PARK BLVD A328      OXNARD, CA 93036

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/15/2022 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 3/11/2022 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 4/18/2022 No Access for Inspection MICHAEL TEMPLE
Sewer 4/18/2022 No Access for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 5/4/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/4/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/2/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/2/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 3/2/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/15/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 3/15/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/15/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 3/15/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/24/2023 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 4/24/2023 Partial Approval MATTHEW NELSON
Green Building Rough 4/24/2023 Approved MATTHEW NELSON
HVAC-Rough 4/24/2023 Approved MATTHEW NELSON
Insulation 5/12/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 6/14/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/14/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/17/2023 Corrections Issued JENNIFER RABUCHIN
Final 11/17/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/17/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 11/17/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 11/17/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/23/2024 Approved MISAEL ESPARZA
Final 2/23/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 2/23/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready MISAEL ESPARZA
Final 4/5/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/5/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/12/2024 Approved JENNIFER RABUCHIN
Final 4/12/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 4/12/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/12/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved JENNIFER RABUCHIN