1425 W 12TH ST #118 90015
Certificate Information: 1425 W 12TH ST #118 90015
- Application / Permit
- 21016-20000-15944
- Plan Check / Job No.
- B21VN07873
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Single Family
- Work Description
- REPAIR TERMITE AND WATER DAMAGED EXTERIOR RAISED FLOOR PATIO AND ITS COVERING MATERIALS AT UNIT 118 (1ST FLOOR).
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/29/2021
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 7/6/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 7/20/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 7/21/2021 | APPLICANT |
| Issued | 9/3/2021 | APPLICANT |
| Permit Finaled | 11/24/2021 | TIMOTHY BUXTON |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/12/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Trifecta Painting & Construction; Lic. No.: 878758-B | 15021 VENTURA BLVD #864 SHERMAN OAKS, CA 91403 |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/13/2021 | Conditional Approval | JONATHAN QUACH |
| Wood Frame | 10/15/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 10/20/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | TIMOTHY BUXTON |
| Final | 11/24/2021 | Permit Finaled | TIMOTHY BUXTON |
| Smoke Detectors | 11/24/2021 | Approved | TIMOTHY BUXTON |