2287 W MOSS AVE 90065

Certificate Information: 2287 W MOSS AVE 90065

Application / Permit
21016-20000-15917
Plan Check / Job No.
B21VN07854
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 11`'-8" X 19'-10" DETACHED 1-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 6/21/2021 JENNIFER LEE
Corrections Issued 6/23/2021 JENNIFER LEE
Plan Check Approved 8/2/2021 JENNIFER LEE
Issued 8/3/2021 APPLICANT
Building Plans Picked Up 8/6/2021 APPLICANT
CofO in Progress 3/8/2022 CHARLES BOGHOSKHAN
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/1/2021 STEVE MELGAR
Permit Cleared 7/1/2021 STEVE MELGAR
Sewer availability Cleared 7/1/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/7/2021 STEVE MELGAR
Specific Plan Cleared 7/23/2021 DYLAN LAWRENCE
Grading Pre-Inspection Cleared 7/28/2021 JENNIFER LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/19/2021 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 10/4/2021 Partial Approval BRAD BESCOS
ELECTRICAL-Rough 10/4/2021 Corrections Issued BRAD BESCOS
Green Building Rough 10/4/2021 Not Ready for Inspection BRAD BESCOS
HVAC-Rough 10/4/2021 Not Ready for Inspection BRAD BESCOS
PLUMBING-Rough 10/4/2021 Approved BRAD BESCOS
Underground Mechanical 10/4/2021 Approved BRAD BESCOS
BUILDING-Rough-Frame 10/19/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/19/2021 Conditional Approval HAMIK HARTOUNIAN
Insulation 10/19/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/19/2021 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 10/26/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 10/26/2021 Approved HAMIK HARTOUNIAN
Shower Pan 10/26/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/9/2021 Approved THOMAS LOGRASSO
Final 1/24/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 1/24/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/24/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/24/2022 Approved HAMIK HARTOUNIAN
Final 3/7/2022 OK to Issue CofO CHARLES BOGHOSKHAN
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Approved CHARLES BOGHOSKHAN