1248 1/2 W 41ST ST 90037

Certificate Information: 1248 1/2 W 41ST ST 90037

Application / Permit
21016-20000-15897
Plan Check / Job No.
B21VN07840
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 30' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 6/21/2021 JENNIFER LEE
Corrections Issued 6/23/2021 JENNIFER LEE
Plan Check Approved 9/7/2021 JENNIFER LEE
Issued 9/7/2021 APPLICANT
Building Plans Picked Up 9/8/2021 APPLICANT
CofO in Progress 4/8/2022 HORACE FULTZ
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/13/2021 THOMAS LANG
Address approval Cleared 8/16/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/16/2021 THOMAS LANG
Permit Cleared 8/18/2021 THOMAS LANG
Construction near power lines Cleared 8/27/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/26/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 10/26/2021 Approved SABAS ALONSO
Underground Mechanical 11/10/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/17/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 11/17/2021 Approved SABAS ALONSO
Wood Frame 11/17/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/19/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 11/19/2021 Approved SABAS ALONSO
Insulation 11/24/2021 Corrections Issued SHAVONNE ESPINOZA
Green Building Rough 12/1/2021 Approved SABAS ALONSO
Insulation 12/1/2021 Approved SABAS ALONSO
Deputy Wood Construction 12/20/2021 Conditional Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Approved SABAS ALONSO
Drywall Nailing 12/23/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 12/23/2021 Partial Approval SABAS ALONSO
Underground Mechanical 12/29/2021 Approved SABAS ALONSO
Shower Pan 1/12/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 1/13/2022 Approved AMY COLIN
Final 2/28/2022 Corrections Issued AMY COLIN
Green Building Final 2/28/2022 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Not Ready AMY COLIN
Smoke Detectors 2/28/2022 Approved AMY COLIN
ELECTRICAL-Final 3/4/2022 Approved SABAS ALONSO
Gas Test 3/4/2022 Approved SABAS ALONSO
HVAC-Final 3/4/2022 Corrections Issued SABAS ALONSO
PLUMBING-Final 3/4/2022 Approved SABAS ALONSO
Final 3/8/2022 Corrections Issued SABAS ALONSO
Green Building Final 3/8/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved SABAS ALONSO
Final 3/17/2022 OK to Issue CofO SABAS ALONSO