119 S MARTEL AVE 90036
Certificate Information: 119 S MARTEL AVE 90036
- Application / Permit
- 21016-20000-15874
- Plan Check / Job No.
- B21VN07825
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: CONVERT THE (E) 397 SQ. FT. DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER GCS656852.2(e)(1)(A). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 5/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/22/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/4/2021 | LUISANGEL VALENZUELA |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 10/29/2021 | APPLICANT |
| CofO in Progress | 5/8/2023 | LILIANA PORTILLO |
| Permit Finaled | 5/11/2023 | DEROLD HAUFF |
| CofO Issued | 5/11/2023 | DEROLD HAUFF |
| Permit Finaled | 5/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 6/24/2021 | LAUREN PADICK |
| CPC | Cleared | 6/24/2021 | LAUREN PADICK |
| Address approval | Cleared | 6/29/2021 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | JEREMY CHOK |
| Sewer availability | Cleared | 6/29/2021 | JEREMY CHOK |
| HPOZ | Cleared | 7/15/2021 | DANIEL MATA |
| Construction near power lines | Cleared | 9/24/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Livewell Remodeling & Construction; Lic. No.: 1049024-B | 4365 MAMMOTH AVE APT 205 SHERMAN OAKS, CA 91423 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/17/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/17/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 12/12/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 12/12/2022 | Approved | MICHAEL LEWIS |
| Shower Pan | 12/12/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/13/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/16/2022 | Approved | MICHAEL LEWIS |
| Green Building Rough | 12/16/2022 | Approved | MICHAEL LEWIS |
| METHANE-Rough | 12/16/2022 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/16/2022 | Approved | MICHAEL LEWIS |
| Insulation | 12/30/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 1/13/2023 | Approved | MICHAEL LEWIS |
| Final | 4/24/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 4/24/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 4/24/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/1/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 5/1/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 5/1/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 5/1/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/5/2023 | Approved | LILIANA PORTILLO |
| Final | 5/5/2023 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 5/5/2023 | Approved | LILIANA PORTILLO |