8208 N LINDLEY AVE 91335
Certificate Information: 8208 N LINDLEY AVE 91335
- Application / Permit
- 21016-20000-15834
- Plan Check / Job No.
- B21VN07798
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' GARAGE AND (N) 2-STORY 12'4" X 20' 2-STORY ADDITION (795 SF) TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | JEFFREY TANGONAN |
| Corrections Issued | 7/3/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 7/9/2021 | APPLICANT |
| Applicant returned to address corrections | 6/29/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 3/13/2023 | MADISON ODELL |
| Issued | 3/16/2023 | APPLICANT |
| CofO in Progress | 12/18/2023 | JEFFREY BULL |
| Permit Finaled | 4/17/2024 | DANIEL ORRANTE |
| CofO Issued | 4/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 2/28/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/28/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/17/2023 | Partial Approval | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 3/20/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/20/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/20/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/30/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 5/30/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 5/30/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 5/30/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 5/30/2023 | Approved | JEFFREY BULL |
| Insulation | 6/1/2023 | Approved | JEFFREY BULL |
| Shower Pan | 6/1/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 6/7/2023 | Approved | JEFFREY BULL |
| Pre-Inspection | 6/7/2023 | Approved | JEFFREY BULL |
| Final | 9/20/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/20/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 9/20/2023 | Approved | JEFFREY BULL |
| Final | 12/18/2023 | OK to Issue CofO | JEFFREY BULL |