8208 N LINDLEY AVE 91335

Certificate Information: 8208 N LINDLEY AVE 91335

Application / Permit
21016-20000-15834
Plan Check / Job No.
B21VN07798
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' GARAGE AND (N) 2-STORY 12'4" X 20' 2-STORY ADDITION (795 SF) TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 3/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Assigned to Plan Check Engineer 7/2/2021 JEFFREY TANGONAN
Corrections Issued 7/3/2021 JEFFREY TANGONAN
Building Plans Picked Up 7/9/2021 APPLICANT
Applicant returned to address corrections 6/29/2022 JEFFREY TANGONAN
Plan Check Approved 3/13/2023 MADISON ODELL
Issued 3/16/2023 APPLICANT
CofO in Progress 12/18/2023 JEFFREY BULL
Permit Finaled 4/17/2024 DANIEL ORRANTE
CofO Issued 4/17/2024 DANIEL ORRANTE
Permit Finaled 4/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/19/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/20/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 9/12/2022 CARLOS AGUILERA
Low Impact Development Cleared 2/28/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/28/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/17/2023 Partial Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 3/20/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 3/20/2023 Approved SEAN HAUPT
PLUMBING-Rough 3/20/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 5/30/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 5/30/2023 Approved JEFFREY BULL
Green Building Rough 5/30/2023 Approved JEFFREY BULL
HVAC-Rough 5/30/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 5/30/2023 Partial Approval JEFFREY BULL
PLUMBING-Rough 5/30/2023 Approved JEFFREY BULL
Insulation 6/1/2023 Approved JEFFREY BULL
Shower Pan 6/1/2023 Approved JEFFREY BULL
Drywall Nailing 6/7/2023 Approved JEFFREY BULL
Pre-Inspection 6/7/2023 Approved JEFFREY BULL
Final 9/20/2023 Corrections Issued JEFFREY BULL
Green Building Final 9/20/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 9/20/2023 Approved JEFFREY BULL
Final 12/18/2023 OK to Issue CofO JEFFREY BULL