527 N MANSFIELD AVE 90036
Certificate Information: 527 N MANSFIELD AVE 90036
- Application / Permit
- 21016-20000-15794
- Plan Check / Job No.
- B21VN07757
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-8" x 19'-10" DETTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- Issued on 3/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | PINANK PATEL |
| Corrections Issued | 6/18/2021 | PINANK PATEL |
| Applicant returned to address corrections | 7/23/2021 | PINANK PATEL |
| Applicant returned to address corrections | 9/9/2021 | PINANK PATEL |
| Plan Check Approved | 3/18/2022 | PINANK PATEL |
| Issued | 3/22/2022 | APPLICANT |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/30/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/30/2021 | RIDWAN HARDY |
| Address approval | Cleared | 2/22/2022 | CELINA MORENO |
| Sewer availability | Cleared | 2/22/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | CELINA MORENO |
Contact Information
| Contractor | Mazzeti Builders Inc; Lic. No.: 1047845-B | 8610 CHALMERS DR #104 LOS ANGELES, CA 90035 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2022 | No Access for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/11/2022 | Corrections Issued | SCOTT FINNILA |
| Pre-Inspection | 4/14/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 6/17/2024 | Approved | RUBEN PEREZ |
| Footing/Foundation/Slab | 6/25/2024 | Approved | ROBERT NILES |
| BUILDING-Rough-Frame | 8/5/2024 | Corrections Issued | ROBERT NILES |
| ELECTRICAL-Rough | 8/5/2024 | Corrections Issued | ROBERT NILES |
| Green Building Rough | 8/5/2024 | Approved | ROBERT NILES |
| HVAC-Rough | 8/5/2024 | Not Ready for Inspection | ROBERT NILES |
| METHANE-Rough | 8/5/2024 | Approved | ROBERT NILES |
| PLUMBING-Rough | 8/5/2024 | Approved | ROBERT NILES |
| Rough-Elec/Plmb/HVAC | 8/5/2024 | Not Ready for Inspection | ROBERT NILES |
| Insulation | 9/3/2024 | Approved | ROBERT NILES |
| Interior/Exterior Lathing | 9/3/2024 | Approved | ROBERT NILES |
| Drywall Nailing | 9/10/2024 | Approved | ROBERT NILES |
| Interior/Exterior Lathing | 10/7/2024 | Approved | PETER RUBIO |
| Shower Pan | 10/7/2024 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 5/28/2025 | Partial Approval | PETER RUBIO |
| ELECTRICAL-Final | 5/28/2025 | Corrections Issued | PETER RUBIO |
| Final | 5/28/2025 | Not Ready for Inspection | PETER RUBIO |
| Green Building Final | 5/28/2025 | Approved | PETER RUBIO |
| HVAC-Final | 5/28/2025 | Corrections Issued | PETER RUBIO |
| PLUMBING-Final | 5/28/2025 | Not Ready for Inspection | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | PETER RUBIO |
| Service/Power Release | 5/28/2025 | Not Required | PETER RUBIO |
| Smoke Detectors | 5/28/2025 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 6/3/2025 | Not Ready for Inspection | PETER RUBIO |
| ELECTRICAL-Final | 6/3/2025 | Not Ready for Inspection | PETER RUBIO |
| Final | 6/3/2025 | Not Ready for Inspection | PETER RUBIO |
| HVAC-Final | 6/3/2025 | Not Ready for Inspection | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | PETER RUBIO |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | PETER RUBIO |
| ELECTRICAL-Final | 9/17/2025 | Corrections Issued | PETER RUBIO |
| Final | 9/17/2025 | Corrections Issued | PETER RUBIO |
| HVAC-Final | 9/17/2025 | Approved | PETER RUBIO |
| PLUMBING-Final | 9/17/2025 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Not Ready | PETER RUBIO |
| Service/Power Release | 9/17/2025 | Not Required | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 5/1/2026 | SGSOV Not Ready | PETER RUBIO |
| ELECTRICAL-Final | 5/18/2026 | Approved | PETER RUBIO |
| Final | 5/18/2026 | OK for TCO | PETER RUBIO |
| HVAC-Final | 5/18/2026 | Approved | PETER RUBIO |
| PLUMBING-Final | 5/18/2026 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | PETER RUBIO |
| Service/Power Release | 5/18/2026 | Not Required | PETER RUBIO |