1340 S GENESEE AVE 90019
Certificate Information: 1340 S GENESEE AVE 90019
- Application / Permit
- 21016-20000-15779
- Plan Check / Job No.
- B21VN07738
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR ALTERATION TO CONVERT A STUDY TO A BATHROOM AND TO CONVERT A PORTION OF THE LIVINGROOM TO A BEDROOM.
- Permit Issued
- Issued on 12/16/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/29/2022
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | LUIS RINCON |
| Corrections Issued | 7/7/2021 | LUIS RINCON |
| Applicant returned to address corrections | 11/14/2021 | ZAW HAN |
| Plan Check Approved | 12/2/2021 | SHANGQIN XIE |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| Issued | 12/16/2021 | APPLICANT |
| Permit Finaled | 4/28/2022 | JOSE AVILA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/14/2021 | RENZ SORIANO |
| Tenant Habitability Plan | Cleared | 11/23/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Inspire Concepts Inc; Lic. No.: 1037765-B | 1037 SOUTH SHERBOURNE DR LOS ANGELES, CA 90035 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/28/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/28/2021 | Corrections Issued | JOSE AVILA |
| Shower Pan | 12/28/2021 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 12/28/2021 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/30/2021 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/30/2021 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 1/12/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/12/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 2/15/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 4/8/2022 | Not Ready for Inspection | JOSE AVILA |
| Final | 4/8/2022 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 4/8/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/8/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 4/8/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 4/19/2022 | Approved | JOSE AVILA |
| Final | 4/19/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 4/19/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 4/19/2022 | Approved | JOSE AVILA |
| Final | 4/28/2022 | Permit Finaled | JOSE AVILA |