6945 N ENFIELD AVE 91335

Certificate Information: 6945 N ENFIELD AVE 91335

Application / Permit
21016-20000-15653
Plan Check / Job No.
B21VN07683
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE 31'-5" x 18'-0" (E) 524 SQ. FT. DETACHED GARAGE WITH ATTACHED STORE ROOM INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
CofO Corrected on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/29/2021 SARKIS HARABEDIAN
Corrections Issued 7/1/2021 SARKIS HARABEDIAN
Building Plans Picked Up 7/2/2021 APPLICANT
Plan Check Approved 10/1/2021 SARKIS HARABEDIAN
Issued 11/1/2021 APPLICANT
CofO in Progress 9/13/2024 JEFFREY BULL
Re-Activate Permit 11/21/2024 JOHN JANSON
CofO Issued-Status Void 11/21/2024 JOHN JANSON
Permit Finaled-Status Void 11/21/2024 JOHN JANSON
Permit Finaled 11/21/2024 JOHN JANSON
CofO Corrected 11/21/2024 JOHN JANSON
Permit Finaled 11/21/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/13/2021 GABRIEL ROBLES
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Construction within easement Cleared 9/13/2021 RIDWAN HARDY
Sewer availability Cleared 9/13/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/22/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2023 Approved JEFFREY BULL
Pre-Inspection 12/26/2023 Approved JEFFREY BULL
Deputy Drilled-In Anchors 3/13/2024 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 3/20/2024 Approved JEFFREY BULL
PLUMBING-Rough 4/4/2024 Corrections Issued JEFFREY BULL
Underground Mechanical 4/5/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 5/13/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 5/13/2024 Approved JEFFREY BULL
Green Building Rough 5/13/2024 Approved JEFFREY BULL
HVAC-Rough 5/13/2024 Approved JEFFREY BULL
PLUMBING-Rough 5/13/2024 Approved JEFFREY BULL
Insulation 5/16/2024 Partial Approval JEFFREY BULL
Drywall Nailing 5/21/2024 Approved JEFFREY BULL
Shower Pan 5/30/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 6/5/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Not Ready MORRIS JACKSON
Final 8/22/2024 Corrections Issued JEFFREY BULL
Green Building Final 8/22/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 8/22/2024 Approved JEFFREY BULL
Final 9/13/2024 OK to Issue CofO JEFFREY BULL