6945 N ENFIELD AVE 91335
Certificate Information: 6945 N ENFIELD AVE 91335
- Application / Permit
- 21016-20000-15653
- Plan Check / Job No.
- B21VN07683
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE 31'-5" x 18'-0" (E) 524 SQ. FT. DETACHED GARAGE WITH ATTACHED STORE ROOM INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Corrected on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 7/1/2021 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| Plan Check Approved | 10/1/2021 | SARKIS HARABEDIAN |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 9/13/2024 | JEFFREY BULL |
| Re-Activate Permit | 11/21/2024 | JOHN JANSON |
| CofO Issued-Status Void | 11/21/2024 | JOHN JANSON |
| Permit Finaled-Status Void | 11/21/2024 | JOHN JANSON |
| Permit Finaled | 11/21/2024 | JOHN JANSON |
| CofO Corrected | 11/21/2024 | JOHN JANSON |
| Permit Finaled | 11/21/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/13/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2023 | Approved | JEFFREY BULL |
| Pre-Inspection | 12/26/2023 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 3/13/2024 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 4/4/2024 | Corrections Issued | JEFFREY BULL |
| Underground Mechanical | 4/5/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/13/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 5/13/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 5/13/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 5/13/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 5/13/2024 | Approved | JEFFREY BULL |
| Insulation | 5/16/2024 | Partial Approval | JEFFREY BULL |
| Drywall Nailing | 5/21/2024 | Approved | JEFFREY BULL |
| Shower Pan | 5/30/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 6/5/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Not Ready | MORRIS JACKSON |
| Final | 8/22/2024 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 8/22/2024 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 8/22/2024 | Approved | JEFFREY BULL |
| Final | 9/13/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 9/13/2024 | Approved | JEFFREY BULL |