33 E 25TH AVE 90291

Certificate Information: 33 E 25TH AVE 90291

Application / Permit
21016-20000-15627
Plan Check / Job No.
B21VN07670
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) 3-STORY SINGLE FAMILY DWELLING & ADD (N) ELEVATOR. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/2/2021
Issuing Office
Valley
Current Status
Permit Finaled on 10/8/2024

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 COLIN LOREDO
Corrections Issued 7/13/2021 COLIN LOREDO
Quality Review Completed 7/14/2021 OMID HEDAYAT
Building Plans Picked Up 7/16/2021 APPLICANT
Plan Check Approved 11/2/2021 COLIN LOREDO
Issued 11/2/2021 APPLICANT
Permit Finaled 10/7/2024 MICHAEL ALLEN

Permit Application Clearance Information

Specific Plan Cleared 8/2/2021 BINDU KANNAN
Coastal Zone Cleared 8/5/2021 ANNA VIDAL
Miscellaneous Cleared 8/5/2021 ANNA VIDAL
Miscellaneous Cleared 8/5/2021 ANNA VIDAL
ZA Case Cleared 8/5/2021 ANNA VIDAL

Contact Information

Contractor Joint Design Build Llc; Lic. No.: 1064585-B 1142 ONEONTA DR      LOS ANGELES, CA 90065

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2022 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 3/10/2022 Partial Approval KENNETH NAGLE
PLUMBING-Rough 7/8/2022 No Access for Inspection DAVID FEILER
PLUMBING-Rough 7/12/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 7/15/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 1/18/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 3/9/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 3/9/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/3/2023 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 4/5/2023 Partial Approval CLAYTON GRAHAM
Shower Pan 4/5/2023 Approved CLAYTON GRAHAM
Footing/Foundation/Slab 8/18/2023 Conditional Approval HERBERT GIRON
Deputy Reinf. Concrete 8/21/2023 Conditional Approval JESUS RODRIGUEZ
Final 8/5/2024 Corrections Issued HERBERT GIRON
Green Building Final 8/5/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 8/5/2024 Corrections Issued HERBERT GIRON
Final 10/7/2024 Permit Finaled MICHAEL ALLEN
Smoke Detectors 10/7/2024 Approved MICHAEL ALLEN