33 E 25TH AVE 90291
Certificate Information: 33 E 25TH AVE 90291
- Application / Permit
- 21016-20000-15627
- Plan Check / Job No.
- B21VN07670
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E) 3-STORY SINGLE FAMILY DWELLING & ADD (N) ELEVATOR. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/8/2024
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | COLIN LOREDO |
| Corrections Issued | 7/13/2021 | COLIN LOREDO |
| Quality Review Completed | 7/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Plan Check Approved | 11/2/2021 | COLIN LOREDO |
| Issued | 11/2/2021 | APPLICANT |
| Permit Finaled | 10/7/2024 | MICHAEL ALLEN |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/2/2021 | BINDU KANNAN |
| Coastal Zone | Cleared | 8/5/2021 | ANNA VIDAL |
| Miscellaneous | Cleared | 8/5/2021 | ANNA VIDAL |
| Miscellaneous | Cleared | 8/5/2021 | ANNA VIDAL |
| ZA Case | Cleared | 8/5/2021 | ANNA VIDAL |
Contact Information
| Contractor | Joint Design Build Llc; Lic. No.: 1064585-B | 1142 ONEONTA DR LOS ANGELES, CA 90065 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/3/2022 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 3/10/2022 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 7/8/2022 | No Access for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/12/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 1/18/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 3/9/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/9/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/3/2023 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 4/5/2023 | Approved | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 8/18/2023 | Conditional Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 8/21/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Final | 8/5/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 8/5/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 8/5/2024 | Corrections Issued | HERBERT GIRON |
| Final | 10/7/2024 | Permit Finaled | MICHAEL ALLEN |
| Smoke Detectors | 10/7/2024 | Approved | MICHAEL ALLEN |