7740 N FARMDALE AVE 91605
Certificate Information: 7740 N FARMDALE AVE 91605
- Application / Permit
- 21016-20000-15559
- Plan Check / Job No.
- B21VN07643
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20' X 18' DETACHED GARAGE AND STORAGE INTO A (N) 323 SQ. FT. ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | PARISA ZAHABI |
| Corrections Issued | 6/19/2021 | PARISA ZAHABI |
| Plan Check Approved | 7/21/2021 | PARISA ZAHABI |
| Issued | 7/22/2021 | APPLICANT |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| CofO in Progress | 12/26/2024 | MATTHEW NELSON |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
| CofO Issued | 1/9/2025 | RUBEN SALAS |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/22/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/14/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/25/2023 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 9/25/2023 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 9/25/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 9/25/2023 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/30/2023 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/30/2023 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 11/30/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 11/30/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 4/5/2024 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 4/5/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/1/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 7/1/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 7/1/2024 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/5/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/5/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/5/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/5/2024 | Approved | MATTHEW NELSON |
| Insulation | 8/5/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/5/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 8/5/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/14/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 8/14/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/21/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/19/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 12/19/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 12/19/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/19/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 12/19/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 12/19/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/26/2024 | Approved | MATTHEW NELSON |
| Final | 12/26/2024 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 12/26/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/26/2024 | Approved | MATTHEW NELSON |
| Service/Power Release | 12/26/2024 | Approved | MATTHEW NELSON |