4640 N ALONZO AVE 91316

Certificate Information: 4640 N ALONZO AVE 91316

Application / Permit
21016-20000-15401
Plan Check / Job No.
B21VN07551
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD. REMOVE WALL BETWEEN KITCHEN AND DINING. REPLACE INTERIOR STAIRS. RAISE FAMILY RM FLOOR TO BE LEVELED. REPLACE WINDOWS AND DOORS. REMODEL BALCONIES. LOWER THE ENTRANCE ROOF. REMOVE ATTACHED DECK AND PATIO. REMODEL BATHROOM TO CREATE TWO BATHROOMS. WORK PER ENGINEER.
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/18/2021 ROSENDO MEDINA
Corrections Issued 6/19/2021 ROSENDO MEDINA
Applicant returned to address corrections 7/23/2021 ROSENDO MEDINA
Plan Check Approved 7/26/2021 ROSENDO MEDINA
Issued 7/26/2021 APPLICANT
Building Plans Picked Up 7/27/2021 APPLICANT
CofO in Progress 11/23/2021 DAVID SANDOVAL
Permit Finaled 11/29/2021 MICHAEL SMITH
CofO Issued 11/29/2021 MICHAEL SMITH
Permit Finaled 11/29/2021 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/23/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/23/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/23/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/23/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/23/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/24/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 7/13/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 7/22/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 8/4/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/4/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 8/4/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 8/6/2021 Corrections Issued DAVID SANDOVAL
HVAC-Rough 8/6/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 8/6/2021 Approved DAVID SANDOVAL
Shower Pan 8/6/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 8/11/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Approved RONALD COWAN
Footing/Foundation/Slab 8/11/2021 Approved RONALD COWAN
HVAC-Rough 8/11/2021 Approved RONALD COWAN
Interior/Exterior Lathing 8/12/2021 Partial Approval ASHLEY THOMPSON
Drywall Nailing 9/1/2021 Partial Approval RONALD COWAN
Interior/Exterior Lathing 9/1/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 11/5/2021 Approved RONALD COWAN
Final 11/5/2021 Corrections Issued RONALD COWAN
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Approved RONALD COWAN
Smoke Detectors 11/5/2021 Approved RONALD COWAN
Final 11/15/2021 Not Ready for Inspection PETER FOLLING
Final 11/23/2021 OK to Issue CofO DAVID SANDOVAL